The final ESA milestone was extended to be consistent with previous project schedule extension due to the last government shutdown (the EIS timing was extended, which necessitated an extension of MMPA dates). Having the EIS, MMPA, and ESA dates coincide will streamline the process compared to how it currently exists. If NMFS is able to work with FERC and AGDC on all marine-mammal-related permitting issues concurrently, it will save delays caused by the need to reinitiate formal section 7 consultation based upon changes in the action (e.g. alterations to mitigation measures that will almost certainly occur). Therefore, NMFS is seeking to change the due date for the ESA section 7 Biological Opinion from 1/12/19 to 6/4/20, the date that the MMPA IHA is scheduled to be published in the Federal Register. NMFS notes that our Biological Opinion is not valid until the MMPA IHA is issued anyway. It is believed that this extension of the ESA date actually saves time by avoiding the potential need for re-initiating consultation. Please see below for answers to the review questions above: 1 - Is the project sponsor concerned with the date change? The project sponsor (AGDC) was made aware of the date change. Their concern is mainly related to how this change impacts FERC's EIS schedule. As noted above, the EIS schedule was changed to adjust for the prior government shutdown. The changes to the ESA date is to align it with the currently published MMPA date for publication of the final rule (6/4/20). The MMPA dates were also previously adjusted to account for the change in the EIS schedule. As the MMPA date change was not an issue for FERC's EIS schedule, it is not thought that the change in ESA dates to be consistent with MMPA dates would adversely impact the EIS schedule. 2 - Does the date change affect any other aspects of the permitting timetable? If so, did you coordinate with the affected agencies? The reason for the date change is to be consistent with other changes that have been made to the permitting timetable. The date for the overall project and EIS had shifted, which shifted the dates for MMPA, so the ESA date is shifting to be consistent with those changes. Therefore, there should be no other effects to the permitting timetable due to the date change. 3 - Have any issues related to this date change been documented in the project’s CPP or discussed at the project-specific CERPO meeting? There haven't been project-specific CERPO meetings, but FERC, AGDC, and the DOC/NOAA/NMFS CERPO have all been made aware of the change. The change can be documented in the next quarterly update to the CPP. 4 - Is there opportunity for the permitting timetable to be adjusted to make up for the time lost as a result of this delay? This is not applicable. The permitting timetable was previously adjusted and this extension request is to ensure that the final ESA date is consistent with those previous changes. 5 - Has your agency CERPO and/or the lead agency CERPO for the project been made aware of the delay and the possible effect it may have on the project? Yes, the DOC/NOAA/NMFS CERPO has been made aware of the change and there were no concerns.
PROJECT WEBSITE: http://alaska-lng.com/
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/13/2023
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Pipelines
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Federal Energy Regulatory Commission
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of Commerce, National Oceanic and Atmospheric Administration
Department of Homeland Security, US Coast Guard
Department of the Interior, Bureau of Land Management
Department of the Interior, Fish and Wildlife Service
Department of the Army, US Army Corps of Engineers - Regulatory
Department of Energy, Office of Fossil Energy
Department of the Interior, National Park Service
Department of Energy
Description:
The Alaska LNG Project is comprised of the following integrated and interdependent facilities: a liquefied natural gas (LNG) terminal in Southcentral Alaska designed to produce up to 20 million metric tons per annum of LNG; an approximately 807-mile, 42-inch diameter gas pipeline; a gas treatment plant (GTP) within the Prudhoe Bay Unit (PBU) on the North Slope; an approximately 1-mile, 60-inch diameter gas transmission line connecting the GTP to the PBU gas production facility; and an approximately 63 mile, 32-inch diameter gas transmission line connecting the GTP to the Point Thomson gas production facility. The mainline of the Alaska LNG Project will traverse over 800 miles from the GTP on the North Slope of Alaska through several boroughs before it crosses Cook Inlet and connects with the liquefaction plant and marine terminal in Nikiski, Alaska.
Fast-41 Initiation Notice
- Document located at: https://elibrary.ferc.gov/idmws/common/OpenNat.asp?fileID=14666498.
Project Application and Supporting Documents
- Project Application, FERC Docket No. CP17-178-000 (submitted 04/17/2017). Document located at: https://elibrary.ferc.gov/idmws/common/OpenNat.asp?fileID=14568607.
- Supporting Documents to Project Application and Additional Project-related filings and issuances can be found on FERC’s eLibrary website by searching under Docket No. CP17-178.
Federal Agency Actions
- Federal Energy Regulatory Commission, Notice of Application (issued 05/01/2017). Document located at: https://elibrary.ferc.gov/idmws/common/opennat.asp?fileID=14578591.
- Federal Energy Regulatory Commission, Notice of Schedule for Environmental Review of the Project (issued 03/12/2018). Document located at: https://elibrary.ferc.gov/idmws/common/opennat.asp?fileID=14838969.
- Federal Energy Regulatory Commission, Notice of Revised Schedule for Environmental Review of the Project (issued 08/31/2018). Document located at: https://elibrary.ferc.gov/idmws/common/opennat.asp?fileID=15013558.
- Federal Energy Regulatory Commission, Notice of Anticipated Schedule of Final Order for the Project (issued 08/31/2018). Document located at: https://elibrary.ferc.gov/idmws/common/opennat.asp?fileID=15013581.
- Federal Energy Regulatory Commission, Notice of Revised Schedule for Environmental Review of the Project (issued 02/28/2019). Document located at: https://elibrary.ferc.gov/idmws/common/opennat.asp?fileID=15172046.
- Federal Energy Regulatory Commission, Draft Environmental Impact Statement (issued 06/28/2019). Document located at: https://www.ferc.gov/draft-environmental-impact-statement-alaska-lng-project.
- Federal Energy Regulatory Commission, Final Environmental Impact Statement (issued 03/06/2020). Document located at: https://www.ferc.gov/industries-data/natural-gas/final-environmental-impact-statement-0.
- Federal Energy Regulatory Commission, Order Granting Authorization under Section 3 of the Natural Gas Act (issued 05/21/2020). Document located at: https://elibrary.ferc.gov/idmws/common/opennat.asp?fileID=15540301.
FERC Litigation
- None filed.
For improved transparency, FERC is providing this supplemental table to reflect the additional federal authorizations that may be required for the Alaska LNG Project.
Additional Federal Agency Permitting Timetable for the Alaska LNG Project | |||
Responsible Agency | Federal Permit/Review | Status | Applicable Timelines |
US Coast Guard | Letter of Recommendation | Complete | Receipt of Letter of Intent: May 15, 2014 Receipt of Waterway Suitability Assessment: March 18, 2016 Letter of Recommendation to FERC: August 17, 2016 |
Last updated September 16, 2020
Milestone: Conclusion of ESA Consultation
Requested extensions greater than 30 days for this Action are shown below:
Conclusion of ESA Consultation by 144 days
From: 01/12/2020
To: 06/04/2020