USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Portions of this site may be affected due to a lapse in appropriations and associated shutdown/furloughs. Please monitor this page for updates on site availability and operating status.

Milestone Extension: Section 106 Review

Submitted by permits-admin on

Providing data entry assistance to DOI per FPISC email...Action is now complete.

Milestone
Section 106 consultation concluded (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: Bureau of Land Management Desert Quartzite Home Page

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
08/04/2020

4 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

The Project would be located approximately 2.75 miles southwest of the City of Blythe, just south of the Interstate 10 freeway, in Riverside County, California.  The Project involves construction of a 450 MW solar facility and a 3 mile long 230 kilovolt transmission line that would connect with Southern California Edison’s Colorado Substation.  After construction, the Project would occupy up to 2,673 acres of BLM land and 154 acres of private land under the jurisdiction of the County of Riverside. Once completed, the Project would also include an operations and maintenance building, an on-site substation, internal access roads, and ancillary facilities. 

field_status
System Comments
Furthest out Original Target Date: 06/29/2019
Milestone: Section 106 consultation concluded

Requested extensions greater than 30 days for this Action are shown below:

Section 106 consultation concluded by 194 days
From: 12/05/2019
To: 01/09/2020
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Section 106 consultation concluded (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Section 106 consultation concluded (Agency Action)
Current Target Date: