We did not receive SHPO Concurrence on Eligibility and Effect Determinations until December 17 which has resulted in more time needed to complete the MOA with the various signatories and partners for the project.
There are no milestones to display.
PROJECT WEBSITE: E-Planning
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/29/2020
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
Major Infrastructure Projects
LEAD AGENCY
Department of the Interior, Bureau of Land Management
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
Department of the Army, US Army Corps of Engineers - Regulatory
Description:
The 690MW/ac Gemini Solar Project, once installed at full capacity, will be the largest solar photovoltaic (“PV”) project in the State of Nevada. The project site is located approximately 25 miles northeast of the Las Vegas metropolitan area, immediately south of the Moapa River Indian Reservation in an unincorporated area of Clark County, Nevada. Interstate 15 (I-15) is located less than ½ mile west of the project site. The NV Energy Crystal Substation and an NV Energy high-voltage transmission line are located less than four miles to the west.
Milestone: Section 106 consultation concluded
Requested extensions greater than 30 days for this Action are shown below:
Section 106 consultation concluded by 126 days
From: 12/18/2019
To: 02/28/2020