Description:
Change from Pause to In-Progress: The Boise River Basin Feasibility Study EIS was un-paused on 4/8/2020 after an additional alternative was added. The project had been paused since 12/13/2019 due to an alternative in the EIS was found infeasible. Reclamation coordinated with our project partner/sponsor (Idaho Water Resource Board) prior to un-pausing of the project and was briefed on the updated target completion date. The delay will not have an effect on project permitting.
Milestones:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Water Resources
CATEGORY
Project Category
MIP Only
Major Infrastructure Projects
LEAD AGENCY
Department of the Interior, Bureau of Reclamation
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
Department of the Army, US Army Corps of Engineers - Regulatory
Description:
The Boise River Basin Feasibility Study EIS was un-paused on 4/8/2020 after an additional alternative was added. The project had been paused since 12/13/2019 due to an alternative in the EIS was found infeasible. Reclamation coordinated with our project partner/sponsor (Idaho Water Resource Board) prior to un-pausing of the project and was briefed on the updated target completion date. The delay will not have an effect on project permitting.
-Issuance of Lead Agency Record of Decision
The responsible agency of this Action, Department of the Interior Bureau of Reclamation, must indicate if Elevation Procedures were used for this extension.