USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

EO 13807 Elevation Procedures for Date Extensions: Endangered Species Act Consultation (DOI-FWS)

Submitted by ccunningham@usbr.gov on
Action
Project Name: Responsible Agency:
Fish and Wildlife Service
Agency Status: Participating
Status:
In Progress
POC Name:
Kathleen Hendicks
POC Title:
Asst. State Supervisor

Description:

Coordination between FWS and BOR developed the following schedule:

Draft BA to FWS June 19, Draft BA back to BoR July 3rd, Final BA consultation package to FWS July 24, FWS transmittal of BO to BoR December 7.

As of 6/5/20, BoR is updating the EIS and BA so we've pushed dates out 2 weeks to allow FWS SOL for BA review and 135 days for formal consultation and delivery of the BO.

Milestones:

ESA Consultation Request Package Submitted (Agency Action)
Completed Date:
FWS determines ESA Consultation Package is Complete - Formal (Agency Action)
Completed Date:
ESA Consultation Concludes (Agency Action)
Current Target Date:
Milestone
ESA Consultation Concludes (Agency Action)
Current Target Date:
Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE

0 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Water Resources

SECTOR
Water Resources

Project Category

CATEGORY
Project Category MIP Only
Major Infrastructure Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Reclamation

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Description:

The Boise River Basin Feasibility Study EIS was un-paused on 4/8/2020 after an additional alternative was added. The project had been paused since 12/13/2019 due to an alternative in the EIS was found infeasible. Reclamation coordinated with our project partner/sponsor (Idaho Water Resource Board) prior to un-pausing of the project and was briefed on the updated target completion date. The delay will not have an effect on project permitting.

field_status
System Comments
The following milestones have been extended 30 days past the current final target completion date for the following Action: Endangered Species Act Consultation (DOI-FWS)

-Conclusion of ESA Consultation

The responsible agency of this Action, Department of the Interior Fish and Wildlife Service, must indicate if Elevation Procedures were used for this extension.
Missed Date Process
No
Missed Date Triggered by Extension
No
Response Date
Original Milestone
ESA Consultation Concludes (Agency Action)
Current Target Date: