USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Milestone Extension: Right-of-Way Authorization (DOI-BLM)

Submitted by fmarcell@blm.gov on

As I mentioned on the FAST-41 call with Jim Cason Thursday, January 23rd, we discussed two weeks ago, January 8th (and previous calls in December) that NextEra had not provided BLM and its contractor (Logan Simpson) the needed information concerning their technology changes to 3.0 MW turbines for Alternative 2.  BLM had expected the information by December 1, 2019 in order to complete the analysis for the Final EIS.  NextEra finally sent the data requested Friday, December 27th. With the holiday period, not much FO or SO review commenced until January 6, 2020 (following the end of the holiday period).  The delay in receiving the needed information equals a five-week loss of time.

Action
Project Name: Responsible Agency:
Bureau of Land Management
Status:
In Progress
POC Name:
Jim Stobaugh
POC Title:
Project Manager
POC Email:

Description:

BLM is responding to an application for a right-of-way on public lands for a wind energy facility. If the BLM offers a right-of-way grant to the applicant, the target date for this action will be the offer date of the right-of-way grant to the applicant for their signature.

Milestones:

Initial application received (Agency Action)
Completed Date:
Completed application received (Agency Action)
Completed Date:
Final decision/agency action (Agency Action)
Current Target Date:
Milestone
Final decision/agency action (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: ePlanning BLM NM website

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
08/14/2020

4 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects
Major Infrastructure Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

Description:

The purpose of the Borderlands Wind Project is to construct, operate and maintain the energy-generating infrastructure in Catron County, New Mexico sufficient to provide up to 100 megawatts (MW) of renewable wind energy to the electrical transmission grid in the Southwest.

field_status
System Comments
Furthest out
Original Target Date: 08/04/2020
Milestone: Notice to proceed

Requested extensions greater than 30 days for this Action are shown below:

Issuance of decision for permit/approval extended by 41
From: 08/04/2020
To: 09/14/2020
Missed Date Process
No
Missed Date Triggered by Extension
No