March 16th government to government consultation with the Zuni Tribe was canceled due to the coronavirus fears. BLM has asked the Tribe about consulting in via video or conference call under the circumstances but the Tribe wants a face to face meeting.
The Tribe is also a cooperating agency on the project and has been sent all NEPA documents for review and comment.
The NM SHPO is encouraging BLM to work with the Tribe in anticipation of things possibly “opening up”. The SHPO and BLM are the only required signatories.
Milestones:
PROJECT WEBSITE: ePlanning BLM NM website
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
08/14/2020
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
Major Infrastructure Projects
LEAD AGENCY
Department of the Interior, Bureau of Land Management
Description:
The purpose of the Borderlands Wind Project is to construct, operate and maintain the energy-generating infrastructure in Catron County, New Mexico sufficient to provide up to 100 megawatts (MW) of renewable wind energy to the electrical transmission grid in the Southwest.
Original Target Date: 07/03/2020
Milestone: Issuance of Lead Agency Record of Decision
Requested extensions greater than 30 days for this Action are shown below:
Issuance of Lead Agency Record of Decision extended by 42
From: 07/03/2020
To: 08/14/2020