USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Milestone Extension: Environmental Impact Statement (EIS)

Submitted by ryan_hathaway@… on

March 16th government to government consultation with the Zuni Tribe was canceled due to the coronavirus fears. BLM has asked the Tribe about consulting in via video or conference call under the circumstances but the Tribe wants a face to face meeting.

The Tribe is also a cooperating agency on the project and has been sent all NEPA documents for review and comment.

The NM SHPO is encouraging BLM to work with the Tribe in anticipation of things possibly “opening up”.  The SHPO and BLM are the only required signatories.

Action
Project Name: Responsible Agency:
Bureau of Land Management
Agency Status: Participating
Status:
In Progress
POC Name:
Jim Stobaugh
POC Email:
Public Participation Website:

Milestones:

Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action)
Completed Date:
Scoping (Agency Action)
Completed Date:
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action)
Completed Date:
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
Completed Date:
Issuance of Lead Agency Record of Decision (Agency Action)
Current Target Date:
Milestone
Issuance of Lead Agency Record of Decision (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: ePlanning BLM NM website

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
08/14/2020

4 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects
Major Infrastructure Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

Description:

The purpose of the Borderlands Wind Project is to construct, operate and maintain the energy-generating infrastructure in Catron County, New Mexico sufficient to provide up to 100 megawatts (MW) of renewable wind energy to the electrical transmission grid in the Southwest.

field_status
System Comments
Furthest out
Original Target Date: 07/03/2020
Milestone: Issuance of Lead Agency Record of Decision

Requested extensions greater than 30 days for this Action are shown below:

Issuance of Lead Agency Record of Decision extended by 42
From: 07/03/2020
To: 08/14/2020
Missed Date Process
No
Missed Date Triggered by Extension
No