FAST-41 Missed Date: Environmental Impact Statement (EIS)

Submitted by Anonymous on

Final Required Milestone Date of 01/24/2020 for Issuance of Lead Agency Record of Decision has passed by 5 business days

Action
Project Name: Responsible Agency:
Bureau of Ocean Energy Management
Status:
Paused
POC Name:
Mary Boatman
POC Title:
Environmental Protection Specialist
Public Participation Website:

Milestones:

Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action)
Completed Date:
Scoping (Agency Action)
Completed Date:
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action)
Current Target Date:
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
Current Target Date:
Issuance of Lead Agency Record of Decision (Agency Action)
  • Non-conformance Explanation:
    Missed Date Explanation (Published 10/21/2021): The 10/20/2021 completion date for "Issuance of Lead Agency Record of Decision" was missed because the Executive Director did not timely receive a  request to modify the completion date. 42 U.S.C. 4370m-2(c)(2)(D)(i)(III) & (ii). Consultations under Section 106 of the National Historic Preservation Act are ongoing. Consulting parties requested additional time to review the Section 106 Memorandum of Agreement (MOA). The Record of Decision cannot be issued until the completion of the Section 106 process (i.e., execution of the MOA). In accordance with 42 U.S.C. 4370m-2(c)(2)(F)(ii), BOEM has established an alternative completion date of 11/23/2021.
Alternative Completion Date:
11/23/2021
Milestone
Issuance of Lead Agency Record of Decision (Agency Action)
  • Non-conformance Explanation:
    Missed Date Explanation (Published 10/21/2021): The 10/20/2021 completion date for "Issuance of Lead Agency Record of Decision" was missed because the Executive Director did not timely receive a  request to modify the completion date. 42 U.S.C. 4370m-2(c)(2)(D)(i)(III) & (ii). Consultations under Section 106 of the National Historic Preservation Act are ongoing. Consulting parties requested additional time to review the Section 106 Memorandum of Agreement (MOA). The Record of Decision cannot be issued until the completion of the Section 106 process (i.e., execution of the MOA). In accordance with 42 U.S.C. 4370m-2(c)(2)(F)(ii), BOEM has established an alternative completion date of 11/23/2021.
Alternative Completion Date:
11/23/2021
Project

PROJECT WEBSITE: South Fork Wind Farm - Deepwater Wind

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Paused

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PAUSED

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE

9 out of 9

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects
Major Infrastructure Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Environmental Protection Agency

Environmental Protection Agency

Description:

The purpose of the South Fork Wind Farm (the Project) is to generate electricity from an offshore wind farm and transmit it to the existing East Hampton Substation, part of the Long Island Power Authority (LIPA) electric transmission and distribution system in East Hampton, New York. The Project addresses the need identified by LIPA for new sources of power generation that can cost-effectively and reliably supply the South Fork of Suffolk County, Long Island, as an alternative to constructing new transmission facilities. The Project will also help LIPA achieve its renewable energy goals. The Project will enable Deepwater South Fork to fulfill its contractual commitments to LIPA pursuant to a Power Purchase Agreement (PPA) executed in 2017 resulting from LIPA's technology-neutral competitive bidding process.

The South Fork Wind Farm is located in federal waters on the Outer Continental Shelf (OCS), specifially in Bureau of Ocean Energy Management (BOEM) Renewable Energy Lease Area OCS-A 0486, approximately 19 miles southeast of Block Island, Rhode Island, and approximately 35 miles east of Montauk Point, New York; The South Fork Export Cable is located on the OCS, in New York State Territorial Waters, and in the Town of East Hampton, New York.

field_status
System Comments
Final Required Milestone Date of 01/24/2020 for Issuance of Lead Agency Record of Decision has passed by 5 business days
Approver Comments
The missed milestone completion date or delay was attributable to reasons beyond the control of the agency.
Previous Action Status
New Action Status
Missed Date Process
No
Missed Date Triggered by Extension
No
New Milestone
Issuance of Lead Agency Record of Decision (Agency Action)
  • Non-conformance Explanation:
    Missed Date Explanation (Published 10/21/2021): The 10/20/2021 completion date for "Issuance of Lead Agency Record of Decision" was missed because the Executive Director did not timely receive a  request to modify the completion date. 42 U.S.C. 4370m-2(c)(2)(D)(i)(III) & (ii). Consultations under Section 106 of the National Historic Preservation Act are ongoing. Consulting parties requested additional time to review the Section 106 Memorandum of Agreement (MOA). The Record of Decision cannot be issued until the completion of the Section 106 process (i.e., execution of the MOA). In accordance with 42 U.S.C. 4370m-2(c)(2)(F)(ii), BOEM has established an alternative completion date of 11/23/2021.
Alternative Completion Date:
11/23/2021
Response Date