USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Portions of this site may be affected due to a lapse in appropriations and associated shutdown/furloughs. Please monitor this page for updates on site availability and operating status.

FAST-41 Missed Date: Section 106 Review

Submitted by Anonymous on

Final Required Milestone Date of 12/18/2019 for Section 106 consultation concluded has passed by 5 business days

Action
Project Name: Responsible Agency:
Bureau of Land Management
Agency Status: Declined as a Participating agency
Status:
Paused
POC Name:
Justin DeMaio
POC Title:
Las Vegas FO Archaeologist
POC Email:
Action Outcome:
Executed memorandum of agreement or programmatic agreement or other conclusion to resolve adverse effects reached
SHPO:

Nevada

Description:

The Las Vegas Field Office will work with the Nevada SHPO on developing a Memorandum of Agreement (MOA), on the impacts to historic sites and effects to the Old Spanish National Historic Trail.

Milestones:

Consultation initiated with SHPO/THPO (Agency Action)
Completed Date:
Section 106 consultation concluded (Agency Action)
Current Target Date:
Milestone
Section 106 consultation concluded (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: E-Planning

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/29/2020

5 out of 5

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects
Major Infrastructure Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Description:

The 690MW/ac Gemini Solar Project, once installed at full capacity, will be the largest solar photovoltaic (“PV”) project in the State of Nevada. The project site is located approximately 25 miles northeast of the Las Vegas metropolitan area, immediately south of the Moapa River Indian Reservation in an unincorporated area of Clark County, Nevada. Interstate 15 (I-15) is located less than ½ mile west of the project site. The NV Energy Crystal Substation and an NV Energy high-voltage transmission line are located less than four miles to the west.

field_status
System Comments
Final Required Milestone Date of 12/18/2019 for Section 106 consultation concluded has passed by 5 business days
Approver Comments
The missed milestone completion date or delay was attributable to reasons beyond the control of the agency
Previous Action Status
New Action Status
Missed Date Process
No
Missed Date Triggered by Extension
No
New Milestone
Section 106 consultation concluded (Agency Action)
Current Target Date:
Response Date