USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

FAST-41 Missed Date: Section 10 Rivers and Harbors Act of 1899 and Section 404 Clean Water Act

Submitted by Anonymous on

Final Required Milestone Date of 09/30/2019 for Final Verification/Permit Decision Rendered has passed by 5 business days

Action
Project Name: Responsible Agency:
US Army Corps of Engineers - Regulatory
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
Paused
POC Name:
Mike Dombroskie
POC Title:
Project Manager

Description:

USACE Baltimore District

The Philadelphia and Baltimore Districts of the U.S. Army Corps of Engineers are processing applications for Department of the Army permits pursuant to Section 10 of the Rivers and Harbors Act of 1899 for construction activities in and under navigable waters of the United States, specifically the Delaware River, Delaware Canal, Lehigh River, Lehigh Canal, and the Susquehanna River.  Pursuant to Section 404 of the Clean Water Act, discharges of dredged and/or fill material into other jurisdictional waters of the United States in the Commonwealth of Pennsylvania are eligible for authorization under the Pennsylvania State Programmatic General Permit.  Jurisdictional waters in the State of New Jersey greater than 1,000 feet landward of the ordinary high water mark of the Delaware River are state-assumed waters for purposes of the Clean Water Act and the New Jersey Department of Environmental Protection is responsible for issuing Section 404 authorization in these waters.

Milestones:

Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action)
Completed Date:
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action)
Completed Date:
Milestone Details

A complete application was received on 08 August.

Publication of Public Notice (Agency Action)
Completed Date:
Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date:
Milestone Details

A Department of the Army permit cannot be issued until the supplemental NEPA document is completed and consultation pursuant to Section 106 of the National Historic Preservation Act is completed; FERC has paused the Section 106 review action on the Permitting Timeline pending receipt of additional cultural resource information and an implementation plan from the project sponsor.  If required information is not received from state/federal agencies and/or the applicant at least 60 days prior to the 90-day deadline specified in the Energy Policy Act of 2005, the district will consider this delay and adjust the decision deadline to allow a 60-day review once all required documentation/information is received.  The district is continuing its evaluation while awaiting information necessary to make its decision on the permit application.

Milestone
Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date:
Milestone Details

A Department of the Army permit cannot be issued until the supplemental NEPA document is completed and consultation pursuant to Section 106 of the National Historic Preservation Act is completed; FERC has paused the Section 106 review action on the Permitting Timeline pending receipt of additional cultural resource information and an implementation plan from the project sponsor.  If required information is not received from state/federal agencies and/or the applicant at least 60 days prior to the 90-day deadline specified in the Energy Policy Act of 2005, the district will consider this delay and adjust the decision deadline to allow a 60-day review once all required documentation/information is received.  The district is continuing its evaluation while awaiting information necessary to make its decision on the permit application.

Project

PROJECT WEBSITE: http://penneastpipeline.com

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/27/2018

4 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Pipelines

SECTOR
Pipelines

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Federal Energy Regulatory Commission

LEAD AGENCY
Federal Energy Regulatory Commission

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Civil Works

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

PennEast Pipeline (Docket No. CP15-558-000) would provide an additional 1.0 Bcf/d of natural gas transportation service through construction of:  (1) 115.1 miles of pipeline from Pennsylvania to New Jersey; (2) 2.1 miles of various lateral pipelines; and (3) a new compressor station.

Project Application and Supporting Documents

Federal Agency Actions

FERC Litigation

  • None filed.

 

Last updated March 28, 2020

field_status
System Comments
Final Required Milestone Date of 09/30/2019 for Final Verification/Permit Decision Rendered has passed by 5 business days
Approver Comments
The missed milestone completion date or delay was attributable to reasons beyond the control of the agency.
Previous Action Status
New Action Status
Missed Date Process
No
Missed Date Triggered by Extension
No
New Milestone
Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date:
Milestone Details

A Department of the Army permit cannot be issued until the supplemental NEPA document is completed and consultation pursuant to Section 106 of the National Historic Preservation Act is completed; FERC has paused the Section 106 review action on the Permitting Timeline pending receipt of additional cultural resource information and an implementation plan from the project sponsor.  If required information is not received from state/federal agencies and/or the applicant at least 60 days prior to the 90-day deadline specified in the Energy Policy Act of 2005, the district will consider this delay and adjust the decision deadline to allow a 60-day review once all required documentation/information is received.  The district is continuing its evaluation while awaiting information necessary to make its decision on the permit application.

Response Date