USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Milestone Extension: Section 106 Review

Submitted by fmarcell@blm.gov on

The consultation with the Nevada SHPO is taking much longer than anticipated therefore the completion of this task is going to need more time.

Action
Project Name: Responsible Agency:
Bureau of Land Management
Status:
In Progress
POC Name:
Augrelio Herman Pinales
POC Title:
Project Manager
POC Email:
Public Participation Website:
SHPO:

Nevada

Description:

The 500MW/ac Yellow Pine Solar Project (YPSP), located on approximately 3,000 acres of public lands managed by the BLM, Southern Nevada District, Las Vegas Field Office. The YPSP would provide renewable energy to the electrical transmission grid at a newly constructed substation, the Trout Canyon Substation (TCS), owned by GridLiance West, LLC (GLW).

Milestones:

Consultation initiated with SHPO/THPO (Agency Action)
Completed Date:
Section 106 consultation concluded (Agency Action)
Current Target Date:
Milestone
Section 106 consultation concluded (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: DOI-BLM-NV-S010-2017-0110-EIS (Yellow Pine)

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/21/2020

4 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects
Major Infrastructure Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

On October 21, 2011, Boulevard Associates, LLC, a subsidiary of NextEra Energy Resources, LLC (NextEra), filed an application for a right-of-way (ROW) grant (N-90788) with the Bureau of Land Management (BLM) Southern Nevada District Office for the Sandy Valley Solar Project on 3,272 acres of land . The Sandy Valley Solar Project has not been built to date; however, the application was filed prior to the BLM’s Final Solar Programmatic Environmental Impact Statement (Final Solar PEIS) (BLM and U.S. Department of Energy [DOE] 2012), and as a pending solar application at the time of this publication, the project is not subject to the decisions adopted by the Record of Decision (ROD) for Solar Energy Development in Six Southwestern States (BLM 2012). On June 24, 2016, Yellow Pine Solar, LLC (herein called the Applicant), a subsidiary of NextEra, submitted an amended application with a new project name, the Yellow Pine Solar Project (YPSP, or project). The Applicant is proposing to develop the YPSP in order to construct, operate, and maintain an
efficient, economic, reliable, safe, and environmentally sound solar-powered generating facility. The YPSP would be in Clark County, Nevada, completely on land managed by the BLM. Based on preliminary discussions with the BLM and initial evaluation of resource concerns, areas to the northwest of the original application area are being included to provide more flexibility for conflict avoidance. The Applicant has amended its original ROW application to include a larger, amended application area (herein called the Application Area) of 9,290 acres. Within the Application Area, construction would occur on a project area comprising approximately 3,000 acres. The Application Area encompasses the original application area, as well as lands proposed as variance areas, as described in the Final Solar PEIS (BLM and DOE 2012). Appendix B, Section B1.2, of the Final Solar PEIS Record of Decision (ROD) states that amendments to pending applications are not subject to the decisions of the ROD if they “are related to avoiding resource or land use conflicts, adapting the project to third-party-owned infrastructure constraints, or using or designating translocation or mitigation lands” (BLM 2012).

field_status
System Comments
Furthest out
Original Target Date: 01/03/2020
Milestone: Section 106 consultation concluded

Requested extensions greater than 30 days for this Action are shown below:

Section 106 consultation concluded extended by 91
From: 01/03/2020
To: 04/03/2020