USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Milestone Extension: Endangered Species Act Consultation (DOI-FWS)

Submitted by jane_ledwin@fws.gov on

Unexpected employee emergency necessitated staff and workload adjustments that resulted in 1 week delay in delivery of the BO.  FWS field and HQ staff coordinated with the applicant and FERC., and there were no concerns from either the applicant or FERC.  The delay did not affect other action or Milestones. The schedule change was coordinated through our Deputy CERPO.

I do not know what, if any, adjustments were made to the CPP.

Action
Project Name: Responsible Agency:
Fish and Wildlife Service
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
Complete
POC Name:
Paul Henson
POC Title:
State Supervisor
POC Email:
Action Outcome:
Biological opinion issued

Description:

We are modifying Milestonte 3 of the ESA consultation to extend the consultation period 30 days. Additional time needed for Consultation due to (1) the amount and scope of additional information about the Project being relayed to the Service by the action agencies, other agencies, tribal entities and the Applicant; (2) the increasing complexity of assessing impacts and their significance based on this additional information; and (3) recent revisions to regulations that implement section 7 of the ESA, that must be applied to consultations underway as of October 28, 2019. The extension should not affect the schedule for the revised date for the EIS.

Milestones:

ESA Consultation Request Package Submitted (Agency Action)
Completed Date:
FWS determines ESA Consultation Package is Complete - Formal (Agency Action)
Completed Date:
ESA Consultation Concludes (Agency Action)
Completed Date:
Milestone
ESA Consultation Concludes (Agency Action)
Completed Date:
Project

PROJECT WEBSITE: Jordan Cove LNG

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/17/2020

9 out of 9

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Pipelines

SECTOR
Pipelines

Project Category

CATEGORY
Project Category FAST-41 Covered Projects
Major Infrastructure Projects

Federal Energy Regulatory Commission

LEAD AGENCY
Federal Energy Regulatory Commission, Office of Energy Projects

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Federal Energy Regulatory Commission

Federal Energy Regulatory Commission

Department of Energy

Department of Energy, Office of Fossil Energy

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

The Jordan Cove LNG Project (Docket No. CP17-495-000) includes the construction and operation of a liquefied natural gas (LNG) export terminal on the North Spit of Coos Bay in Coos County, Oregon.  The terminal would include gas inlet facilities, a metering station, a gas conditioning plant, five liquefaction trains and associated equipment, two full-containment LNG storage tanks, an LNG transfer line, LNG ship loading facilities, a marine slip, a marine offloading facility, a new access channel between the Coos Bay Navigation Channel and the new marine slip, and enhancements to the existing Coos Bay Navigation Channel at four turns.  In addition, the terminal would include emergency and hazard, electrical, security, control, and support systems, administrative buildings, and a temporary workforce housing facility.  The LNG terminal would be designed to liquefy about 1.04 billion cubic feet per day of LNG for export to markets across the Pacific Rim.

The Pacific Connector Gas Pipeline (Docket No. CP-17-494) includes the construction and operation an approximately 235-mile-long, 36-inch-diameter interstate natural gas transmission pipeline and associated aboveground facilities.  The pipeline would originate near Malin in Klamath County, Oregon, traverse Douglas and Jackson Counties, and terminate (at the LNG Terminal) in Coos County, Oregon.  The pipeline would be capable of transporting about 1.2 billion cubic feet per day of natural gas.  The associated aboveground facilities would include the new Klamath Compressor Station (61,500 horsepower) near Malin, Oregon; 3 new meter stations; 5 new pig launchers and receivers; 17 mainline block valves; and a gas control communication system.

Fast-41 Initiation Notice

Project Application and Supporting Documents

Federal Agency Actions

FERC Litigation

  • None filed.

 

For improved transparency, FERC is providing this supplemental table to reflect the additional federal authorizations that may be required for the Jordan Cove LNG Project.  

Additional Federal Agency Authorization Timetable for the Jordan Cove LNG and Pacific Connector Gas Pipeline Project
AgencyPermitStatusApplicable Timelines
U.S. Coast GuardLetter of RecommendationCompletedReceipt of Letter of Intent:  April 2006
Receipt of Water Suitability Assessment:  10/1/17
Letter of Recommendation to FERC:  5/10/18  

 

Federally-Delegated State Authorization Table
AgencyPermitStatusApplicable Timeline
Oregon Department of Envrionmnetal QualityClea Water Act 401 Water Quality CertificationPendingThe state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016) provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
Oregon Department of Envrionmnetal QualityClean Water Act - National Pollutant Discharge Elimination System PermitPendingThe state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016) provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
Oregon Department of Envrionmnetal QualityClean Air Act – Title V Operating Air PermitPendingThe state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016) provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
Oregon Department of Envrionmnetal QualityClean Air Act - New Source Review Permit for LNG TerminalPendingThe state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016) provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
Oregon Department of Land Conservation and DevelopmentCoastal Zone Management Consistency DeterminationPendingThe state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016) provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."

 

Last updated December 30, 2019

field_status
System Comments
Furthest out
Original Target Date: 12/11/2019
Milestone: Conclusion of ESA Consultation

Requested extensions greater than 30 days for this Action are shown below:

Conclusion of ESA Consultation extended by 37 days
From: 01/10/2020
To: 01/17/2020