This extension would allow the proponent time to submit required documentation (survey plats and Joint Use Agreement/Permits for ROW). A detailed survey plat and legal description of where the proposed right of way will be within the existing easements are necessary, to ensure accuracy and to show that all the requirements of the legal description have been met. Given the application is not yet complete, all milestones will need to be pushed out. Coordination with all cooperating agencies on these milestone changes has occurred.
New Mexico
Milestones:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/09/2026
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Broadband
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Indian Affairs
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
Department of the Interior, Bureau of Reclamation
Department of the Interior, Bureau of Land Management
Description:
The Navajo Nation Department of Education proposes to deploy a reliable, affordable, scalable,
and future-proofed broadband network that bridges the digital divide for the foreseeable future in some of the most remote, isolated, high-cost, and difficult to serve areas of the United States. The Navajo Nation Department of Education E-Rate Funded Broadband Project consists of constructing approximately 323 miles of middle mile fiber optic network on the Navajo Nation to connect 17 Head Start entities and 33 libraries with high-speed Internet connectivity to speeds of 1 Gbps or greater.
Original Target Date: 06/06/2025
Milestone: Section 106 consultation concluded (Agency Action)
Requested extensions greater than 30 days for this Action are shown below:
Section 106 consultation concluded (Agency Action) extended by 185
From: 06/06/2025
To: 12/08/2025