The FAST-41 covered Santa Fe Indian School (SFIS) Pueblo Education Network (PEN) Environmental Assessment (EA) has run into issues and needs to extend the Permitting Dashboard milestones. Due to SFIS staffing changes, it has taken time to establish training of new staff and further project execution. Since early summer 2024, consultant contracts and spending were put on hold and has resulted in a number of environmental review and permitting timeline delays. Foremost, Section 106 completion still needs to occur with the Pueblos of Zuni, Acoma, Isleta and Ramah Navajo Leadership and THPOs and NM SHPO on cultural surveys and sensitivity concerns. The permitting dashboard currently identifies Section 106 concluding on 1/15/25, but we now estimate up to six additional months of work that needs to be factored into the permitting dashboard date to reach Section 106 conclusion. This change will have cascading effects to the Final EA/FONSI dates and all other Cooperating Agency Federal Actions and milestone dates.
New Mexico
Milestones:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
10/29/2027
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Broadband
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of Commerce, National Telecommunications and Information Administration
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
Department of the Interior, Bureau of Land Management
Department of the Interior, National Park Service
Department of the Interior, Bureau of Indian Affairs
Department of the Army, US Army Corps of Engineers - Section 408
Description:
The Pueblo Education Network builds middle mile broadband infrastructure for tribes, enabling digital economy participation and effectuating last-mile internet access to homes and anchor institutions and tribal businesses. The Pueblo Education Network also creates a private education network connecting tribal PreK-20 schools and libraries to each other and to national research and education networks, modernizing Indian Education in the global information age. The overall footprint is approximately 324 miles. The project originates in Albuquerque, New Mexico and travels through Isleta Pueblo, Acoma Pueblo, and Zuni Pueblo lands with the fiber path ending at the Zuni Elementary School, Zuni Head Start Building, Zuni Governor’s Office, and Zuni High School. The fiber path will primarily be immediately adjacent to already established roads and will travel through private lands, Bureau of Land Management, US Forest Service, New Mexico State Land Office, Navajo Nation lands at Ramah, and Zuni Pueblo lands.
The Executive Director granted a National Telecommunications and Information Administration (NTIA), request to extend the NEPA; Section 106; Right-of-Way (BLM); NPS Permit; Right-of-Way (FWS Sevilleta NWR); ESA-FWS; Section 404 final completion dates on December 28, 2023. The Executive Director determination is posted here.
The Executive Director granted a National Telecommunications and Information Administration (NTIA), request to extend the NEPA; Section 106; Right-of-Way (BLM); NPS Permit; Right-of-Way (FWS Sevilleta NWR); Section 404 final completion dates on March 28, 2024. The Executive Director determination is posted here.
The Executive Director granted a National Telecommunications and Information Administration (NTIA), request to extend the Right-of-Way (BIA) final completion date on June 26, 2024. The Executive Director determination is posted here.
The Executive Director granted a National Telecommunications and Information Administration (NTIA), request to extend the NEPA; Section 106; NPS Permit; Right-of-Way (FWS); Right-of-Way (BLM); Right-of-Way (BIA Southern Pueblos Agency); Right-of-Way (BIA Zuni Agency); USACE Section 404 final completion date on July 15, 2024. The Executive Director determination is posted here
Original Target Date: 01/31/2024
Milestone: Section 106 consultation concluded (Agency Action)
Requested extensions greater than 30 days for this Action are shown below:
Section 106 consultation concluded (Agency Action) extended by 531
From: 01/15/2025
To: 07/15/2025