Milestone Extension: Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consulta

Submitted by cori.carraway@… on

BOEM adjusted the schedule by 777 days at the project sponsor's request.  All milestones have been adjusted accordingly and BOEM will submit an EDD memo for the changes. 

Action
Project Name: Responsible Agency:
National Oceanic and Atmospheric Administration
Status:
Planned

Milestones:

EFH Consultation Request Submitted – EFH Assessment (Agency Action)
Current Target Date:
Milestone Details

This target milestone date reflects the anticipated date of receipt of the initial EFH Assessment from BOEM.  The EFH consultation request is expected to be concurrent with the cooperating agency review of the Draft EIS.  Meeting this milestone target date is contingent upon NOAA Fisheries receiving an EFH Assessment from BOEM by the date indicated. 

 

 

NOAA determines EFH Assessment is Complete (Agency Action)
Current Target Date:
Milestone Details

The EFH consultation initiation is contingent upon NOAA Fisheries receiving sufficient information (a complete EFH assessment) from BOEM to initiate EFH consultation. 

 

NOAA Issues any EFH Conservation Recommendations (Agency Action)
Current Target Date:
Milestone Details

Issuance of EFH Conservation Recommendations is dependent upon the magnitude of adverse effects and the extent to which BMPs abate those adverse effects. 

 

Milestone
NOAA Issues any EFH Conservation Recommendations (Agency Action)
Current Target Date:
Milestone Details

Issuance of EFH Conservation Recommendations is dependent upon the magnitude of adverse effects and the extent to which BMPs abate those adverse effects. 

 

Project

PROJECT WEBSITE: http://www.KittyHawkOffshore.com

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE

0 out of 10

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Army

Department of the Army, US Army Corps of Engineers - Civil Works

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Environmental Protection Agency

Environmental Protection Agency

Description:

Update: In June 2022, the project name changed from Kitty Hawk Wind Project to Kitty Hawk South Wind Project to reflect the segmenting of the project.

Kitty Hawk Wind, LLC proposes to construct, own, and operate the Kitty Hawk South Offshore Wind Project. The Project will be located in the designated Renewable Energy Lease Area OCS-A 0508 (Lease Area). The Commercial Lease of Submerged Lands for Renewable Energy Development on the Outer Continental Shelf of Lease Area OCS-A 0508 was awarded through the BOEM competitive renewable energy lease auction of the Wind Energy Area offshore of North Carolina. The Lease Area covers 49,536 hectares (ha) and is located 44 kilometers (km) offshore of Corolla, North Carolina.

At this time, the Company is proposing to develop the Kitty Hawk South Offshore Wind Project in the eastern portion of the Lease Area (33,768 ha; referred to as the Wind Development Area), located approximately 61 km east of Corolla, North Carolina and approximately 54 km northeast of Kill Devil Hills, North Carolina. The offshore components of the Project, including the WTGs, offshore substations, and inter-array cables, will be located in federal waters within the Lease Area. The offshore export cable corridor will traverse both federal waters and state territorial waters of Virginia and/or North Carolina. Onshore Project components, including the export cable landfall location(s), onshore export and interconnection cables, and onshore electrical facilities, will be located in one or more of the following:

• City of Virginia Beach, Virginia;
• Dare County, North Carolina;
• Carteret County, North Carolina; and
• Craven County, North Carolina.

A COP for the Project, which includes detailed assessments of environmental, cultural, and historic resources, was submitted to BOEM on April 14, 2022.
Additional Project information is located at www.KittyHawkOffshore.com.

field_status
System Comments
Furthest out
Original Target Date: 07/29/2025
Milestone: NOAA Issues any EFH Conservation Recommendations (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

NOAA Issues any EFH Conservation Recommendations (Agency Action) extended by 777
From: 07/29/2025
To: 09/14/2027
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
NOAA Issues any EFH Conservation Recommendations (Agency Action)
Current Target Date:
Milestone Details

Issuance of EFH Conservation Recommendations is dependent upon the magnitude of adverse effects and the extent to which BMPs abate those adverse effects. 

 

Furthest Original Target Date Milestone
NOAA Issues any EFH Conservation Recommendations (Agency Action)
Current Target Date:
Milestone Details

Issuance of EFH Conservation Recommendations is dependent upon the magnitude of adverse effects and the extent to which BMPs abate those adverse effects.