Milestone Extension: Construction and Operations Plan

Submitted by craig.litteken… on

BOEM is requesting these completion date modifications due to the timing of the Project Sponsor’s submission of a revised Construction and Operations Plan (COP) containing additional data and assessments that BOEM requires prior to issuing a Notice of Intent (NOI) to prepare an Environmental Impact Statement (EIS) under NEPA. BOEM has requested that the revised COP contain certain survey data for one of the proposed cable routes as well as the following assessments: the Navigational Safety Risk Assessment; Historic Resources Visual Effects Assessment for certain facilities; Marine Archaeological Resource Assessment for a particular cable route; and the Terrestrial Archeological Resource Assessment for all routes and facilities in the onshore project design envelope. The Project Sponsor intends to submit the revised COP containing all the requested information on October 27, 2025.

Action
Project Name: Responsible Agency:
Bureau of Ocean Energy Management
Status:
In Progress
POC Name:
Josh Gange
POC Title:
Project Coordinator

Milestones:

Initial application submitted (Applicant Action)
Completed Date:
Application deemed complete (Agency Action)
Completed Date:
Final decision/agency action (Agency Action)
Current Target Date:

Additional Milestones:

Additional Milestones
Agency Review of Initial Application – for Consistency with the NOI Checklist
Current Target Date:
Additional Milestone Details

This milestone documents completion of BOEM's review to determine whether the COP is consistent with the NOI Checklist in accordance with the NEPA regulations at 40 CFR 1501.9 and BOEM's regulations at 30 CFR part 585.

BOEM reviews the COP for consistency with published guidance titled ‘BOEM Guidance on Information Needed for Issuance of a Notice of Intent (NOI) Under the National Environmental Policy Act (NEPA) for a Construction and Operations Plan,’ (the NOI Checklist). Upon completion of the review, BOEM marks this milestone complete and notifies the applicant if the COP lacks any of the necessary information.

Applicant Submits Updated Application for Consistency with the NOI Checklist
Completed Date:
Additional Milestone Details

Project Sponsor submits an updated COP consistent with the NOI Checklist.

Agency Review of Updated Application for Consistency with NOI Checklist
Current Target Date:
Applicant submits an Application Consistent with the NOI Checklist
Current Target Date:
Additional Milestone Details

Project Sponsor submits a COP consistent with the NOI Checklist.

Agency Review of Updated Application for Consistency with NOI Checklist
Current Target Date:
Applicant Submits Updated Application for Consistency with the NOI Checklist
Current Target Date:
Milestone
Final decision/agency action (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: Skipjack Wind

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING

0 out of 0

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Description:

Skipjack Offshore Energy, LLC (SJOE) intends to develop, build, operate, and own (through one or more affiliated special purpose entities) an offshore wind farm located approximately 15 miles off the coast of Delaware within Lease Areas OCS A0519 and OCS A0482. The purpose of the Project is to construct and operate a new offshore wind farm designed to help one or more states within the mid-Atlantic region meet their clean energy goals. The Project would consist of up to 72 wind turbine generators (“WTG”), associated inter-array cabling, new onshore and offshore substations, transmission cables and onshore works for connection to the wholesale electric grid administered by PJM Interconnection L.L.C.

field_status
System Comments
Furthest out
Original Target Date: 10/12/2027
Milestone: Final decision/agency action (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

Final decision/agency action (Agency Action) extended by 274
From: 10/12/2027
To: 07/12/2028
Approver Comments
Executive Director Determination signed on 3/24/25.
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Final decision/agency action (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Final decision/agency action (Agency Action)
Current Target Date: