USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

FAST-41 Missed Date:Section 408 Permit: Completeness Determination (Agency Action)

Submitted by Anonymous on

Agency Milestone Date of 10/26/2026 for Completeness Determination (Agency Action) has passed by 1 business days

Action
Project Name: Responsible Agency:
US Army Corps of Engineers - Section 408
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
Planned
POC Name:
Bonnie Jennings

Milestones:

Initial application submitted (Applicant Action)
Completed Date:
Completeness Determination (Agency Action)
Current Target Date:
Complete application submitted (Applicant Action)
Current Target Date:
Issuance of Decision (Agency Action)
Current Target Date:
Milestone
Completeness Determination (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: Texas Gateway Project Website

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
02/14/2028

0 out of 9

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Pipelines

SECTOR
Pipelines

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Federal Energy Regulatory Commission

LEAD AGENCY
Federal Energy Regulatory Commission

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Army

Department of the Army, US Army Corps of Engineers - Section 408

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of the Interior

Department of the Interior, Bureau of Land Management

Description:

The Project consists of the construction of a new approximately 155-mile-long natural gas pipeline comprised of 36-inch and 42-inch diameter pipe segments originating in Carthage, Texas and terminating in Beauregard Parish, Louisiana. The Project includes three new delivery meter and regulator stations, one new compressor station along Gulf South Pipeline Company’s existing Index 129 pipeline in San Jacinto County, Texas, along with expanding two existing compressor stations in Panola and Sabine Counties, Texas.

field_status
System Comments
Agency Milestone Date of 10/26/2026 for Completeness Determination (Agency Action) has passed by 1 business days
Previous Action Status
New Action Status
Missed Date Process
No
Missed Date Triggered by Extension
No
New Milestone
Completeness Determination (Agency Action)
Current Target Date: