USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

FAST-41 Missed Date:Section 106 Review: Consultation initiated with SHPO/THPO (Agency Action)

Submitted by Anonymous on

Agency Milestone Date of 03/06/2025 for Consultation initiated with SHPO/THPO (Agency Action) has passed by 1 business days

Action
Project Name: Responsible Agency:
Bureau of Indian Affairs
Status:
Planned
POC Name:
Lenora Bates
POC Title:
Realty Specialist
SHPO:

New Mexico

THPO:
Navajo Nation

Milestones:

Consultation initiated with SHPO/THPO (Agency Action)
Current Target Date:
Section 106 consultation concluded (Agency Action)
Current Target Date:
Milestone
Consultation initiated with SHPO/THPO (Agency Action)
Current Target Date:
Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/30/2026

2 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Broadband

SECTOR
Broadband

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Indian Affairs

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Bureau of Land Management

Description:

The Gallup McKinley County School proposes to deploy a reliable, affordable, scalable, and future-proofed broadband network that bridges the digital divide for the foreseeable future in one of the most remote, isolated, high-cost, and difficult to serve areas of the United States. The Gallup McKinley County Schools E-Rate Funded Broadband Project consists of constructing approximately 65 miles of middle mile fiber optic network on the Navajo Nation to connect the school district with high-speed Internet connectivity to speeds of 1 Gbps or greater.

field_status
System Comments
Agency Milestone Date of 03/06/2025 for Consultation initiated with SHPO/THPO (Agency Action) has passed by 1 business days
Approver Comments
Missed date due to lack of information from Project Sponsor to initiate consultation. EDD expected.
Previous Action Status
New Action Status
Missed Date Process
No
Missed Date Triggered by Extension
No
New Milestone
Consultation initiated with SHPO/THPO (Agency Action)
Current Target Date:
Response Date
Reporting Agency