USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

FAST-41 Missed Date:Section 10 Rivers and Harbors Act of 1899 and Section 404 Clean Water Act: Publication of Public Notice (Agency Action)

Submitted by jason.w.steele… on

Triggered missed date from extending Publication of Public Notice (Agency Action) within 30 days of its current target date which was 08/24/2026 and extended to 09/10/2026

Action
Project Name: Responsible Agency:
US Army Corps of Engineers - Regulatory
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
Planned
POC Name:
Krista Sabin
POC Title:
Regulatory Review Officer

Milestones:

Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action)
Completed Date:
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action)
Current Target Date:
Publication of Public Notice (Agency Action)
Current Target Date:
Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date:
Milestone Details

This date is dependent on the following specific actions and milestones:

  • Section 408 Permit (USACE) Issuance of Decision (Agency Action)
  • ESA Consultation Concludes (Agency Action)
  • Section 106 consultation concluded (Agency Action)
  • Official Notice of Availability of a Final EIS (Agency Action)
Milestone
Publication of Public Notice (Agency Action)
Current Target Date:
Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/07/2026

6 out of 7

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Pipelines

SECTOR
Pipelines

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Federal Energy Regulatory Commission

LEAD AGENCY
Federal Energy Regulatory Commission

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Interior

Department of the Interior, National Park Service

Description:

The proposed project would include 14 new pipeline loops, modifications and new compression at 12 existing Southern Natural Gas compressor stations in Mississippi, Alabama, and Georgia, and additional compression at Elba Express’s Jefferson and Rincon Compressor Stations in Georgia. The proposed project would also include constructing and upgrading multiple meter stations and the abandonment and replacement of nine aging compressor units and approximately 2.2 miles of lateral pipeline in Clarke County, Mississippi.  The proposed project would provide 1.323 billion cubic feet per day of incremental firm natural gas transportation capacity for markets in the Southeast. 

field_status
System Comments
Triggered missed date from extending Publication of Public Notice (Agency Action) within 30 days of its current target date which was 08/24/2026 and extended to 09/10/2026
Previous Action Status
New Action Status
Missed Date Process
No
Missed Date Triggered by Extension
Yes
New Milestone
Publication of Public Notice (Agency Action)
Current Target Date: