FAST-41 Missed Date:Endangered Species Act Consultation (DOI-FWS): FWS determines ESA Consultation Package is Complete - Formal (Agency Action)

Submitted by permits-admin on

Agency Milestone Date of 09/11/2022 for FWS determines ESA Consultation Package is Complete - Formal (Agency Action) has passed by 1 business days

Action
Project Name: Responsible Agency:
Fish and Wildlife Service
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
Planned
POC Name:
Shawn Sartorius
POC Title:
Field Supervisor

Description:

The ESA consultation will evaluate the effects of the proposed activities on federally listed species and designated critical habitat. FWS will use BLM's biological assessment to complete consultation on this project. The proposed schedule anticipates evaluation of the preferred or selected alternative/aligment of the project. The currrent schedule includes a 135-day formal consultation period and additional time for BLM to review the draft BO should they do so. Milestone target dates will be confirmed when we determine we have a complete consultation package and can begin the consultation.

Milestones:

ESA Consultation Request Package Submitted (Agency Action)
Completed Date:
FWS determines ESA Consultation Package is Complete - Formal (Agency Action)
Current Target Date:
ESA Consultation Concludes (Agency Action)
Current Target Date:
Milestone
FWS determines ESA Consultation Package is Complete - Formal (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: SunZia Project Website

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
08/24/2023

6 out of 6

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Electricity Transmission

SECTOR
Electricity Transmission

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Description:

The SunZia Project includes two nominal 500-kV transmission lines located on federal, state, and private lands between central New Mexico and central Arizona. The approximately 550-mile-long transmission line route originates at the planned SunZia East Substation in Torrance County, New Mexico, and terminates near the existing Saguaro substation and the existing Pinal Central Substation, both in Pinal County, Arizona. The SunZia Project is located in Socorro, Sierra, Luna, Grant, Hidalgo, and Torrance counties in New Mexico and Graham, Greenlee, Cochise, Pinal, and Pima counties in Arizona.

The SunZia Project will be constructed in two phases and ultimately include two, new, single-circuit, 500 kV transmission lines with the intent of locating both within a single 400-foot-wide right-of-way, where possible. Only one of the two 500-kV circuits will be constructed in Phase 1 and the planned in-service date for the first transmission line is 2025. The first transmission line would be a direct-current (DC) line and the second transmission line would be an alternating-current (AC) line.

Update:

The Executive Director granted a BLM's request to extend the Section 106 consultation "Section 106 Review" completion date because route changes for the Project require modifications to the programmatic agreement needed to conclude the Section 106 consultation. The Executive Director determination is posted here.

field_status
System Comments
Agency Milestone Date of 09/11/2022 for FWS determines ESA Consultation Package is Complete - Formal (Agency Action) has passed by 1 business days
Approver Comments
Confirmed with FWS that the milestone was met and should be marked as complete. FWS acted promptly to mark the action complete as soon as they were notified of the nonconformance flag. Based on OED IPM team discussion, I am exempting this nonconformance since the interim milestone is complete.
Previous Action Status
New Action Status
Missed Date Process
No
Missed Date Triggered by Extension
No
Response Date
Original Milestone

There are no milestones to display.

Furthest Original Target Date Milestone

There are no milestones to display.

Reporting Agency