USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

FAST-41 Covered Projects Postings by Agencies for Hell's Kitchen Critical Minerals & Power

FAST-41 Initiation Notice

Project Information

Project Title

Hell's Kitchen Critical Minerals & Power

Sector

Sector:Mining

 

Project Location Address

Country

Street Address 1

Street Address 2 (Optional)

City

State

Zip Code

County

United States7903 Davis Road CalipatriaCalifornia92233Imperial

 

Coordinates

  • Latitude: 33.220622
    Longitude: 115.580425

 

Project Sponsor Contact Information

  • Company Name/Agency: Controlled Thermal Resources Holdings Inc.
    Project Sponsor: Controlled Thermal Resources (US) Inc.
    Street Address 1 : 124 W 9th Street
    Street Address 2 (Optional): Suite 101
    City: Imperial
    State: California
    Zip Code: 92251
    POC Name: James T. Turner
    POC Title: President
    POC Phone: (760) 604-0433
    POC Email Address: jim.turner@cthermal.com

 

Alternative Point Of Contact (Optional)

No 

 

Project Purpose

The Hell’s Kitchen Critical Minerals & Power Project will provide the first in a series of American minerals extraction and conversion production facilities powered by renewable geothermal energy. This will supply a number of critical minerals that meet market grade requirements. The power plant will use the geothermal brine to produce electrical power from its steam and the direct lithium extraction plant will convert the dissolved lithium into battery-grade lithium hydroxide and/or lithium carbonate for the battery industry.

 

Project Description

The Hell’s Kitchen Critical Minerals & Power Project will convert geothermal brine into steam to generate electrical energy. Both the steam and the electrical energy will be used in the extraction of lithium and other minerals from that same geothermal brine for onsite conversion into battery-grade lithium hydroxide or lithium carbonate.

The Project is located southeast of the Salton Sea, Calipatria, California, centered at approximately latitude 33o13’14.24” N and longitude 115o34’49.53” W. There are no known cultural or historic resources within the Project site, however, monitors will be present for the initial movement of earth at the site for recognition and disposition of those resource types, should any be uncovered. There are known bird nesting areas in the general area of the Salton Sea, however, the project construction and operation are designed to avoid disturbing any nesting areas.

 

Technical and Financial Ability

The Project sponsor includes employees and consultants that have extensive geothermal energy development and production experience including mineral extraction specifically from the Salton Sea geothermal resource. In addition, the sponsor has partnered with highly respected engineering and construction firms to deliver this Project for commercial operation.

The Project sponsor is a new company relying on individual accredited investor support as well as strategic investor support of this first critical mineral extraction and conversion project powered by renewable energy. The sponsor has been successful in raising funds necessary to complete Project development, pilot testing, engineering and design, site characterization and related environmental permitting.

Goldman Sachs and BNP Paribas are engaged to raise the necessary equity and debt for construction, and the Project has received letters of interest for debt from U.S. EXIM and Italian SACE.

 

Summary of Financing, Reviews and Authorizations

The Project has received its State of California Conditional Use Permit under the California Environmental Quality Act and requires a federal CWA Section 404 Permit due to the Army Corps jurisdiction. In conjunction with the federal CWA 404 permit, Project approvals include Endangered Species Act, Section 7 consultation with the US Fish and Wildlife Service (USFWS) as the primary other regulatory agency approval. Building, grading, air emission, and other construction permits are all issued locally and will be secured through Imperial County agencies. The Project sponsor is familiar with and has successfully obtained permits from each of these relevant agencies for exploration and testing well pad construction and pilot plant construction and operation.

The Project is funded by individual accredited investors and strategic investors and will continue to be financed in this manner through close of construction financing.

 

Project Assessment

The Hell’s Kitchen Geothermal and Lithium Extraction Project is a covered project under 42 USC §4370m(6)(A)(iv):
• It is subject to NEPA; the size and complexity of the Project make it likely to benefit from enhanced oversight and coordination. The Project sponsor’s previous experience in obtaining necessary approvals from the Army Corps and USFWS for the exploration well pads and pilot plant demonstrated the need for a framework to coordinate agency efforts and promote adherence to permitting timelines.

 

Form Submitter Contact Information

 

Accept Agreement

Yes

 

Additional details: The FIN is just for Stage 1 and the total investment value of Stage 1 is approximately $2.2B.

Application and Supporting Documents

The applicant and supporting documents were provided to the District in accordance with the permitting timetable.

Information on the status of mitigation measures

Mitigation measures were provided to the District in accordance with the permitting timetable

Description of the status of any litigation

N/A

Information about project-related public meetings, public hearings, and public comment periods

 

The U.S. Army Corps of Engineers, Los Angeles District, Regulatory Division, South Coast Branch received an application for a Department of the Army permit.  The Public Notice can be viewed at the link below: 

 

https://www.spl.usace.army.mil/Media/Public-Notices/Year/2025/

 

 

Project Name:  Hell's Kitchen Critical Minerals and Power Project 

 

Corps File No.:  SPL-2025-00406

 

Waterbody:   Non tidal wetland waters adjacent to relatively permanent waters connected to the Salton Sea. 

 

City:  Niland 

 

County:  Imperial County

 

Mailing Lists:  General and California

 

Comment Period: November 20, 2025, to December 20, 2025

Description of any Federal agency action taken or decision made that materially affects the status of the project

Not available at this time