EO 13807 Elevation Procedures for Date Extensions: Section 106 Review

Submitted by julie.a.alcon@… on
Action
Milestone
Section 106 consultation concluded (Agency Action)
Current Target Date:
Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING

0 out of 0

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Water Resources

SECTOR
Water Resources

Project Category

CATEGORY
Project Category MIP Only
Major Infrastructure Projects

Department of the Army

LEAD AGENCY
Department of the Army, US Army Corps of Engineers - Civil Works

field_status
System Comments
The following milestones have been extended 30 days past the current final target completion date for the following Action: Section 106 Review

-Section 106 consultation concluded

The responsible agency of this Action, Department of the Army US Army Corps of Engineers - Civil Works, must indicate if Elevation Procedures were used for this extension.
Missed Date Process
No
Missed Date Triggered by Extension
No
Response Date
Original Milestone
Section 106 consultation concluded (Agency Action)
Current Target Date: