USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

EO 13807 Elevation Procedures for Date Extensions: Section 106 Review

Submitted by jennifer.bucat… on
Action
Project Name: Document URL: /June%207%2C%202018
Responsible Agency:
Bureau of Ocean Energy Management
Status:
Complete
POC Name:
Brandi Carrier
POC Title:
Deputy Federal Preservation Officer
Action Outcome:
Executed memorandum of agreement or programmatic agreement or other conclusion to resolve adverse effects reached
SHPO:

Massachusetts

Milestones:

Consultation initiated with SHPO/THPO (Agency Action)
Completed Date:
Section 106 consultation concluded (Agency Action)
Completed Date:
Milestone
Section 106 consultation concluded (Agency Action)
Completed Date:
Project

PROJECT WEBSITE: Vineyard Wind Project Website

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/21/2021

8 out of 8

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category MIP Only
Major Infrastructure Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

Other Agencies with Actions or Authorizations:

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

The Vineyard Wind project would involve the construction, operation, maintenance and eventual decommissioning of an up to 800 MW wind energy facility on the Federal Outer Continental Shelf approximately 14 miles southeast of Martha’s Vineyard.  Vineyard Wind’s construction and operations plan (COP) proposes installing up to 100 wind turbine generators, each with a capacity of between 8 and 14 MW. Foundations would be 100 monopiles or up to 10 jacket foundations and the remainder monopiles. The proposed facility would also include one or two offshore substations or electrical service platforms. The Vineyard Wind COP also proposes an export cable from the wind energy facility to one of two potential export cable landfalls: one near the town of Yarmouth and one near the town of Barnstable, both in the Commonwealth of Massachusetts. Onshore construction and staging would take place at the New Bedford Marine Commerce Terminal facility. The turbines would be located in water depths ranging from approximately 37 to 49 meters (approximately 121 to 161 feet).

field_status
System Comments
The following milestones have been extended 30 days past the current final target completion date for the following Action: Section 106 Review

-Section 106 consultation concluded

The responsible agency of this Action, Department of the Interior Bureau of Ocean Energy Management, must indicate if Elevation Procedures were used for this extension.
Missed Date Process
No
Missed Date Triggered by Extension
No
Response Date
Original Milestone
Section 106 consultation concluded (Agency Action)
Current Target Date: