USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

EO 13807 Elevation Procedures for Date Extensions: Section 10 Rivers and Harbors Act of 1899 and Section 404 Clean Water Act

Submitted by jennifer.bucat… on
Action
Project Name: Responsible Agency:
US Army Corps of Engineers - Regulatory
Agency Status: Cooperating under NEPA
Status:
In Progress
POC Name:
Christine Jacek

Description:

A Department of the Army permit is required pursuant to Section 10 of the Rivers and Harbors Act of 1899 for construction activities in, over and under navigable waters of the United States and Section 404 of the Clean Water Act for discharges of dredged or fill material in conjunction with the Vineyard Wind Project.

Milestones:

Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action)
Completed Date:
Milestone Details

The U.S. Army Corps of Engineers, New England District received an application for a Department of the Army permit for the Vineyard Wind Project on December 18, 2018.

Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action)
Completed Date:
Milestone Details

The U.S. Army Corps of Engineers, New England District received a complete application for a Department of the Army permit for the Vineyard Wind Project on December 18, 2018.

Publication of Public Notice (Agency Action)
Completed Date:
Milestone Details

The U.S. Army Corps of Engineers, New England District issued a public notice announcing rescheduled public meetings for the Vineyard Wind Project on February 1, 2019.

Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date:
Milestone Details

The U.S. Army Corps of Engineers, New England District is scheduled to issue a Department of the Army permit decision pursuant to Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act on or before July 21, 2021.  This revised milestone is 90 days after the April 21, 2021 revised BOEM milestone for issuance of a Record of Decision for the Vineyard Wind project.  This date is subject to contingencies including but not limited to completion of consultations pursuant to the Endangered Species Act and the National Historic Preservation Act and issuance by the Commonwealth of Massachusetts of any required approvals pursuant to the Coastal Zone Management Act and the Clean Water Act.  If required information is not received from state/federal agencies and/or the applicant at least 60 days prior to the 90-day deadline specified in the Energy Policy Act of 2005, the district will consider this delay and adjust the decision milestone to allow a 60-day review once all required documentation/information is received. 

Milestone
Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date:
Milestone Details

The U.S. Army Corps of Engineers, New England District is scheduled to issue a Department of the Army permit decision pursuant to Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act on or before July 21, 2021.  This revised milestone is 90 days after the April 21, 2021 revised BOEM milestone for issuance of a Record of Decision for the Vineyard Wind project.  This date is subject to contingencies including but not limited to completion of consultations pursuant to the Endangered Species Act and the National Historic Preservation Act and issuance by the Commonwealth of Massachusetts of any required approvals pursuant to the Coastal Zone Management Act and the Clean Water Act.  If required information is not received from state/federal agencies and/or the applicant at least 60 days prior to the 90-day deadline specified in the Energy Policy Act of 2005, the district will consider this delay and adjust the decision milestone to allow a 60-day review once all required documentation/information is received. 

Project

PROJECT WEBSITE: Vineyard Wind Project Website

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/21/2021

8 out of 8

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category MIP Only
Major Infrastructure Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

Other Agencies with Actions or Authorizations:

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

The Vineyard Wind project would involve the construction, operation, maintenance and eventual decommissioning of an up to 800 MW wind energy facility on the Federal Outer Continental Shelf approximately 14 miles southeast of Martha’s Vineyard.  Vineyard Wind’s construction and operations plan (COP) proposes installing up to 100 wind turbine generators, each with a capacity of between 8 and 14 MW. Foundations would be 100 monopiles or up to 10 jacket foundations and the remainder monopiles. The proposed facility would also include one or two offshore substations or electrical service platforms. The Vineyard Wind COP also proposes an export cable from the wind energy facility to one of two potential export cable landfalls: one near the town of Yarmouth and one near the town of Barnstable, both in the Commonwealth of Massachusetts. Onshore construction and staging would take place at the New Bedford Marine Commerce Terminal facility. The turbines would be located in water depths ranging from approximately 37 to 49 meters (approximately 121 to 161 feet).

field_status
System Comments
The following milestones have been extended 30 days past the current final target completion date for the following Action: Section 10 Rivers and Harbors Act of 1899 and Section 404 Clean Water Act

-Final Verification/Permit Decision Rendered

The responsible agency of this Action, Department of the Army US Army Corps of Engineers - Regulatory, must indicate if Elevation Procedures were used for this extension.
Missed Date Process
No
Missed Date Triggered by Extension
No
Response Date
Original Milestone
Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date:
Milestone Details

The U.S. Army Corps of Engineers, New England District is scheduled to issue a Department of the Army permit pursuant to Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act on or before March 18, 2021.  This revised milestone is 90 days after the December 11, 2020 revised BOEM milestone for issuance of a Record of Decision for the Vineyard Wind project.  This date is subject to contingencies including but not limited to completion of consultations pursuant to the Endangered Species Act and the National Historic Preservation Act and issuance by the Commonwealth of Massachusetts of any required approvals pursuant to the Coastal Zone Management Act and the Clean Water Act.  If required information is not received from state/federal agencies and/or the applicant at least 60 days prior to the 90-day deadline specified in the Energy Policy Act of 2005, the district will consider this delay and adjust the decision milestone to allow a 60-day review once all required documentation/information is received.