EO 13807 Elevation Procedures for Date Extensions: Environmental Impact Statement (EIS)

Submitted by fmarcell@blm.gov on
Action
Project Name: Responsible Agency:
Bureau of Land Management
Status:
In Progress
POC Name:
Miriam Liberatore
POC Title:
Project Manager
POC Email:
Public Participation Website:
Action Outcome:
Issuance of an individual agency ROD

Description:

The BLM will issue a Record of Decision on completion of the EIR-EIS and the protest period, the Section 106 consultation, and the Section 7 ESA consultation.

Milestones:

Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action)
Completed Date:
Scoping (Agency Action)
Completed Date:
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action)
Completed Date:
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
Completed Date:
Issuance of Lead Agency Record of Decision (Agency Action)
Current Target Date:
Milestone
Issuance of Lead Agency Record of Decision (Agency Action)
Current Target Date:
Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
05/03/2021

4 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category MIP Only
Major Infrastructure Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

350-MW photovoltaic solar generation facility with battery storage, proposed on 2,500 acres of public lands, managed by the BLM in the Palm Springs-South Coast Field Office of the California Desert District. Project is in Riverside County, CA.

field_status
System Comments
The following milestones have been extended 30 days past the current final target completion date for the following Action: Environmental Impact Statement (EIS)

-Issuance of Lead Agency Record of Decision

The responsible agency of this Action, Department of the Interior Bureau of Land Management, must indicate if Elevation Procedures were used for this extension.
Missed Date Process
No
Missed Date Triggered by Extension
No
Response Date
Original Milestone
Issuance of Lead Agency Record of Decision (Agency Action)
Current Target Date: