Mining
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/20/2026
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Mining
CATEGORY
LEAD AGENCY
Department of the Army, US Army Corps of Engineers - Regulatory
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
Description:
PROJECT WEBSITE:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/14/2026
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Mining
CATEGORY
LEAD AGENCY
Department of the Interior, Bureau of Land Management
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
Description:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
09/29/2026
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Mining
CATEGORY
LEAD AGENCY
Department of the Army, US Army Corps of Engineers - Regulatory
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
Department of Commerce, National Oceanic and Atmospheric Administration
Description:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
05/25/2027
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Mining
CATEGORY
LEAD AGENCY
Nuclear Regulatory Commission
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Interior, Bureau of Indian Affairs
Description:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/31/2028
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Mining
CATEGORY
LEAD AGENCY
Department of Agriculture, US Forest Service
View FAST-41 Postings by Agencies
Description:
PROJECT WEBSITE:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/12/2026
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Mining
CATEGORY
LEAD AGENCY
Department of the Interior, Bureau of Land Management
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
Description:
PROJECT WEBSITE:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/30/2026
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Mining
CATEGORY
LEAD AGENCY
Department of the Interior, Bureau of Land Management
Description:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/31/2027
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Mining
CATEGORY
LEAD AGENCY
Department of Energy
Description:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/21/2025
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Mining
CATEGORY
LEAD AGENCY
Department of Energy
Description:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/01/2025
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Mining
CATEGORY
LEAD AGENCY
Department of the Army, US Army Corps of Engineers - Regulatory
Other Agencies with Actions or Authorizations:
Department of Defense, US Army Corps of Engineers - Regulatory