Planned
FAST-41 Missed Date:Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consultation: NOAA determines EFH Assessment is Complete (Agency Action)
Agency Milestone Date of 12/01/2022 for NOAA determines EFH Assessment is Complete (Agency Action) has passed by 1 business days
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PLANNED
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
PENDING
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
LEAD AGENCY
California, CalTrans
FAST-41 Missed Date:Section 408 Permit: Completeness Determination (Agency Action)
Agency Milestone Date of 11/21/2022 for Completeness Determination (Agency Action) has passed by 1 business days
FAST-41 Missed Date:Endangered Species Act Consultation (DOI-FWS): FWS determines ESA Consultation Package is Complete - Formal (Agency Action)
Agency Milestone Date of 11/16/2022 for FWS determines ESA Consultation Package is Complete - Formal (Agency Action) has passed by 1 business days
FAST-41 Missed Date:Endangered Species Act Consultation (NOAA-NMFS): NOAA determines ESA Consultation Package is Complete - Formal (Agency Action)
Agency Milestone Date of 11/01/2022 for NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) has passed by 1 business days
FAST-41 Missed Date:Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consultation: NOAA determines EFH Assessment is Complete (Agency Action)
Agency Milestone Date of 10/12/2022 for NOAA determines EFH Assessment is Complete (Agency Action) has passed by 1 business days
FAST-41 Missed Date:Environmental Impact Statement (EIS): Scoping (Agency Action)
Triggered missed date from extending Scoping (Agency Action) within 30 days of its current target date which was 11/07/2022 and extended to 01/29/2024