Planned
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PLANNED
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
PENDING
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY

LEAD AGENCY
Department of Transportation, Federal Highway Administration
Other Agencies with Actions or Authorizations:

States
Description:
FAST-41 Missed Date:Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consultation: NOAA determines EFH Assessment is Complete (Agency Action)
Agency Milestone Date of 03/23/2023 for NOAA determines EFH Assessment is Complete (Agency Action) has passed by 1 business days
FAST-41 Missed Date:Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consultation: NOAA determines EFH Assessment is Complete (Agency Action)
Triggered missed date from extending NOAA determines EFH Assessment is Complete (Agency Action) within 30 days of its current target date which was 04/19/2023 and extended to 05/05/2023
FAST-41 Missed Date:Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consultation: NOAA determines EFH Assessment is Complete (Agency Action)
Agency Milestone Date of 03/20/2023 for NOAA determines EFH Assessment is Complete (Agency Action) has passed by 1 business days
FAST-41 Missed Date:Endangered Species Act Consultation (NOAA-NMFS): NOAA determines ESA Consultation Package is Complete - Formal (Agency Action)
Agency Milestone Date of 03/20/2023 for NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) has passed by 1 business days