Complete
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/13/2021
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Aviation
CATEGORY

LEAD AGENCY
Department of Transportation, Federal Aviation Administration
Description:
FAST-41 Missed Date: Section 404 Clean Water Act
Final Required Milestone Date of 05/22/2020 for Final Verification/Permit Decision Rendered has passed by 5 business days
FAST-41 Missed Date: Section 106 Review
Final Required Milestone Date of 05/12/2020 for Section 106 consultation concluded has passed by 5 business days
FAST-41 Missed Date: Environmental Impact Statement (EIS)
Final Required Milestone Date of 05/08/2020 for Issuance of Lead Agency Record of Decision has passed by 5 business days