FAST-41 Missed Date: Right-of-Way Authorization (DOI-BLM)
Triggered missed date from extending Issuance of decision for permit/approval within 30 days of its current target date which was 07/13/2020 and extended to 08/21/2020
Triggered missed date from extending Issuance of decision for permit/approval within 30 days of its current target date which was 07/13/2020 and extended to 08/21/2020
Triggered missed date from extending Section 106 consultation concluded within 30 days of its current target date which was 07/17/2020 and extended to 07/28/2020
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/13/2021
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Aviation
CATEGORY
LEAD AGENCY
Department of Transportation, Federal Aviation Administration
Final Required Milestone Date of 05/22/2020 for Final Verification/Permit Decision Rendered has passed by 5 business days
Final Required Milestone Date of 05/12/2020 for Section 106 consultation concluded has passed by 5 business days
Final Required Milestone Date of 05/08/2020 for Issuance of Lead Agency Record of Decision has passed by 5 business days