Complete
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/11/2022
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Aviation
CATEGORY

LEAD AGENCY
Department of Transportation, Federal Aviation Administration
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Civil Works
Description:
FAST-41 Missed Date: Section 404 Clean Water Act
Triggered missed date from extending Final Verification/Permit Decision Rendered within 30 days of its current target date which was 04/20/2020 and extended to 05/22/2020
FAST-41 Missed Date: Section 106 Review
Triggered missed date from extending Section 106 consultation concluded within 30 days of its current target date which was 12/18/2019 and extended to 05/12/2020
FAST-41 Missed Date: Environmental Impact Statement (EIS)
Triggered missed date from extending Issuance of Lead Agency Record of Decision within 30 days of its current target date which was 03/27/2020 and extended to 05/08/2020
FAST-41 Missed Date: Right-of-Way Authorization (DOI-BLM)
Triggered missed date from extending Issuance of decision for permit/approval within 30 days of its current target date which was 03/31/2020 and extended to 06/29/2020