Complete
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
08/19/2024
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Aviation
CATEGORY

LEAD AGENCY
Department of Transportation, Federal Aviation Administration
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/28/2021
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Aviation
CATEGORY

LEAD AGENCY
Department of Transportation, Federal Aviation Administration
Description:
FAST-41 Missed Date: Right-of-Way Authorization (DOI-BLM)
Triggered missed date from extending Issuance of decision for permit/approval within 30 days of its current target date which was 07/13/2020 and extended to 08/21/2020
FAST-41 Missed Date: Section 106 Review
Triggered missed date from extending Section 106 consultation concluded within 30 days of its current target date which was 07/17/2020 and extended to 07/28/2020