Tennessee Gas Abandonment and Capacity Restoration

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.


PROJECT STATUS
CANCELLED
SECTOR
Pipelines
CATEGORY
FAST-41 Covered Projects
LEAD AGENCY
Federal Energy Regulatory Commission
Description: 

The Tennessee Gas Abandonment and Capacity Restoration (Docket No. CP15-88-000) includes:  (1) abandonment of 964 miles of mainline pipeline facilities between Louisiana and Ohio; (2) construction and operation of new and replacement pipelines totaling about 15.5 miles in Ohio, Kentucky, Tennessee, and Mississippi; (3) construction of four new natural gas compressor stations in Ohio; (4) construction of two new compressor units at an existing compressor station in Kentucky; and (5) construction of one new compressor unit at an approved compressor station in Kentucky.  

Project Application and Supporting Documents

Federal Agency Actions

FERC Litigation

  • None filed.

 

State Agency Permitting Timetable for the Tennessee Gas Abandonment and Capacity Restoration Project
Responsible State AgencyFederal Permit/ReviewIntermediate Completion DateFinal Completion DateDescription Field
Kentucky Department of Environmental ProtectionSection 401 CWA Review - Water Quality CertificationN/ATBDThe state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016), provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
Ohio Environmental Protection AgencySection 401 CWA Review - Water Quality CertificationN/ATBDThe state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016), provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
Louisiana Department of Environmental QualitySection 402 CWA Review - National Pollutant Discharge Elimination System, Hydrostatic Test Discharge PermitN/ATBDThe state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016), provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
Arkansas Department of Environmental QualitySection 402 CWA Review - National Pollutant Discharge Elimination System, Hydrostatic Test Discharge PermitN/ATBDThe state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016), provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
Mississippi Department of Environmental QualitySection 402 CWA Review - National Pollutant Discharge Elimination System, Hydrostatic Test Discharge PermitN/ATBDThe state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016), provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
Tennessee Department of Environment and ConservationSection 402 CWA Review - National Pollutant Discharge Elimination System, Hydrostatic Test Discharge PermitN/ATBDThe state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016), provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
Tennessee Department of Environment and ConservationSection 402 CWA Review - National Pollutant Discharge Elimination System, Hydrostatic Test Withdrawal PermitN/ATBDThe state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016), provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
Kentucky Department of Environmental ProtectionSection 402 CWA Review - National Pollutant Discharge Elimination System, Hydrostatic Test Discharge PermitN/ATBDThe state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016), provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
Ohio Environmental Protection AgencySection 402 CWA Review - National Pollutant Discharge Elimination System, Hydrostatic Test Discharge PermitN/ATBDThe state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016), provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
Kentucky Department of Environmental ProtectionTitle V CAA Review - Operating Permit for Air EmissionsN/ATBDThe state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016), provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."

 

Last Updated: November 28, 2018

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action
Responsible Agency
Status
Actual Completion Date