North Anna Power Station, Unit 3

PROJECT WEBSITE: http://www.nrc.gov/reactors/new-reactors/col/north-anna.html

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/02/2017

2 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Conventional Energy Production icon

SECTOR
Conventional Energy Production

CATEGORY
FAST-41 Covered Projects

Nuclear Regulatory Commission icon

LEAD AGENCY
Nuclear Regulatory Commission, Office of New Reactors

Description:

Dominion Virginia Power seeks approval for constructing and operating a new ESBWR reactor unit at the North Anna Power Station site to provide additional electricity for use in the midatlantic service areas.  The new unit would be capable of providing an additional 1500 megawatts of baseload electricity.  The combined license was issued on June 2, 2017.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete