Levy Nuclear Plant Units 1 and 2

PROJECT WEBSITE: Levy Nuclear Plant Units 1 and 2

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
10/20/2016

2 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Conventional Energy Production icon

SECTOR
Conventional Energy Production

CATEGORY
FAST-41 Covered Projects

Nuclear Regulatory Commission icon

LEAD AGENCY
Nuclear Regulatory Commission, Office of New Reactors

Description:

Duke Energy Florida LLC seeks approval for constructing and operating two new AP1000 reactor units at the Levy Nuclear Plant site to provide additional electricity for use in the north and central Florida service areas. The two new units would be capable of providing an additional 2200 megawatts of baseload electricity.  The licenses were issued on 10/26/2016.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete