Hudson River Rebuild by Design Project : Resist, Delay, Store, Discharge

PROJECT WEBSITE: NJDEP-Flood Hazard Risk

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.


PROJECT STATUS
COMPLETE
COMPLETION DATE
Oct 09 2017
5 OUT OF 5
ENVIRONMENTAL REVIEW
AND PERMITTING PROCESSES COMPLETED
SECTOR
Water Resources
CATEGORY
FAST-41 Covered Projects
LEAD AGENCY
Housing and Urban Development
Description: 

The Rebuild by Design- Hudson River: Resist, Delay, Store, Discharge project is a comprehensive urban stormwater management strategy to address impacts from coastal storm surge flooding as well as systemic infall rain flooding.  HUD awarded funds to the State of New Jersey for Phase 1 of this comprehensive project.  Phase 1 includes the 1) a master plan for the entire strategy, (2) studies and pilot projects on various aspects of the overall strategy, and (3) the following catalytic projects: coastal defense at Hoboken Station and surroundings, coastal defense at Weehawkin Cove, and pump station and CSO wetland pilot project.  The funded first phase includes the design and environmental impact analysis of the overall comprehensive master plan of the entire project (including the Resist and Delay, Store and Discharge components), and funding for the construction of the Resist components (the catalytic coastal defense projects).  The Delay, Store and Discharge would be implemented by the City of Hoboken in the future.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.

To view Timetable chart, please turn device sideways (landscape)

Overall Project Timetable
STATUS
Schedule
Extension
Ahead of Schedule
Paused

Action Information

For additional information, please select an Action from the Permitting Timetable above.

Action:
Responsible Agency:
Bureau:
Action Status:
SHPO:
Action Identifier:
Action Outcome:
Milestone
Original Target Date
Current Target Date
Milestone Complete