Official US Government Icon

The .gov means it’s official.
Federal government websites often end in .gov or .mil. Before sharing sensitive information, make sure you're on a federal government site.

Secure Site Icon

The site is secure.
The https:// ensures that you are connecting to the official website and that any information you provide is encrypted and transmitted securely.

Gulf LNG Liquefaction Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/31/2019

8 out of 8

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Pipelines icon

SECTOR
Pipelines

CATEGORY
FAST-41 Covered Projects

Federal Energy Regulatory Commission icon

LEAD AGENCY
Federal Energy Regulatory Commission

Description:

The Gulf LNG Liquefaction Project (Docket No. CP15-521-000) is a proposal to construct natural gas liquefaction and LNG export facilities at an existing LNG import terminal in Mississippi.  The facilities include two liquefaction trains to liquefy up to 1.5 Bcf/d, and modifications to Gulf LNG Energy’s terminal and Gulf LNG Pipeline to allow for exports.

Project Application and Supporting Documents

Federal Agency Actions

FERC Litigation

  • None filed.

 

For improved transparency, FERC is providing this supplemental table to reflect the additional federal authorizations that may be required for the Gulf LNG Project.  

Additional Federal Agency Permitting Timetable for the Gulf LNG Project 

Responsible Agency

Federal Permit/Review

Status

Applicable Timelines

U.S. Coast Guard

Letter of Recommendation

Complete

Receipt of Letter of Intent:  June 19, 2015
Receipt of Waterway Suitability Assessment:  October 23, 2015
Letter of Recommendation to FERC:  August 9, 2017

 

State Agency Permitting Timetable for Gulf LNG Liquefaction Project
Responsible State Agency Federal Permit/Review Status Description Field
Mississippi Department of Marine Resources, Coastal Zone Management Office Section 307 CZMA Review Pending The state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016) provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
Mississippi Department of Environmental Quality Section 401 CWA Review - Water Quality Certification Pending The state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016) provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
Mississippi Department of Environmental Quality, Office of Pollution Control Section 402 CWA Review - National Pollutant Discharge Elimination System, Stormwater General Permit Pending The state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016) provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
Mississippi Department of Environmental Quality, Office of Pollution Control Section 402 CWA Review - National Pollutant Discharge Elimination System, Hydrostatic Test Discharge Permit Pending The state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016) provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
Mississippi Department of Environmental Quality Title V CAA Review - Operating Permit for Air Emissions Pending The state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016) provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."

 

Last updated August 8, 2019

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete