Francis S. Gabreski Airport SheltAir Hangar Development, Environmental Assessment

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.


PROJECT STATUS
COMPLETE
SECTOR
Aviation
CATEGORY
DOT Projects
LEAD AGENCY
Department of Transportation
Description: 

The proposed hangar redevelopment project consists of the following:

● Demolition of existing buildings on the SheltAir leasehold (an approximately 13,000 square foot hangar, a 3,500 square foot hangar, and a 1,200 square foot block building);

● Construction of a new approximately 23,000 square foot, single-story, pre-engineered aircraft hangar building and attached approximately 2,250 square foot space for offices, restrooms and other pilot services;

● Rehabilitation of the existing apron for aircraft parking and a vehicular parking area with 57 parking spaces;

● Stormwater infrastructure, lighting for aircraft and vehicular parking areas, and ancillary utility work; and

● 625 square feet of office space to be constructed if needed at a future date in an area on the southwest corner of the proposed hangar building. The impact analysis of this development was included in the evaluations for the overall project.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action
Responsible Agency
Status
Actual Completion Date