Crystal Municipal Airport Airfields and Associated Airport Improvements, Environmental Assessment
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/15/2020
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Aviation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Aviation Administration
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
Department of the Army, US Army Corps of Engineers - Regulatory
Description:
The Sponsor recently completed a Long-Term Comprehensive Plan (LTCP) for the Airport, which was approved by the MAC Board in October 2017. The key planning objectives for the LTCP were to:
•Better align airfield infrastructure to match existing and forecasted activity levels (right-size the airfield);
•Preserve and improve operational capabilities for the current family of aircraft using the facility; and
•Enhance safety by simplifying the runway and taxiway layout.
Information from the recently completed LTCP will be used, as applicable, along with other additional data to be collected and developed as deemed necessary. Project components to be covered as part of the environmental documentation include the following:
•Decommission Runway 14R/32L and convert to parallel taxiway
•Convert portions of Runway 14L/34R blast pads to usable runway
•Reduce length of Runway 06R/24L (turf) to clear Taxiways D & F from the RSA
•Establish LNAV approach to Runway 32R
•Various taxiway improvements and removals
•Expand the FBO apron
•Develop airport land for non-aeronautical use along 63rd Avenue North (work related to this project component will be broken out separately in the fee estimate to allow for a la carte addition or removal)
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|