Atlantic Coast Pipeline, Atlantic Coast Pipeline Amendment, Supply Header, and ACP-Piedmont Lease

PERMITTING DASHBOARD PROJECT POSTING DATE: AUGUST 19, 2016

PROJECT WEBSITE: https://www.dom.com/corporate/what-we-do/atlantic-coast-pipeline

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
02/09/2018

17 out of 17

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Pipelines

SECTOR
Pipelines

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Federal Energy Regulatory Commission

LEAD AGENCY
Federal Energy Regulatory Commission

Other Agencies with Actions or Authorizations:

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of Agriculture

Department of Agriculture, US Forest Service

Department of the Interior

Department of the Interior, National Park Service

Description:

This project consists of four proposals:  Atlantic Coast Pipeline (Docket No. CP15-554-000), Atlantic Coast Pipeline Amendment (Docket No. CP15-554-001), Supply Header (Docket No. CP15-555-000), and ACP-Piedmont Lease (Docket No. CP15-556-000).  Atlantic Coast Pipeline would increase natural gas transportation service by 1.5 Bcf/d in West Virginia, Virginia, and North Carolina through:  (1) construction of 564 miles of pipeline; and (2) three new natural gas compressor stations.  The Atlantic Coast Pipeline Amendment, filed 03/14/2016, amends the Atlantic Coast Pipeline application by adding construction of 80 miles of new natural gas pipeline and revising the pipeline route to include U.S. Forest Service land.  Supply Header would provide 1.5 Bcf/d of additional natural gas transportation service to the Atlantic Coast Pipeline through:  (1) construction of 37.5 miles of natural gas pipeline; and (2) additional capacity at three existing compressor stations in Pennsylvania and West Virginia.  The ACP-Piedmont Lease consists of a proposal to lease capacity on an existing pipeline in North Carolina, which will be used by Atlantic Coast Pipeline.

Project Application and Supporting Documents

Federal Agency Actions

FERC Litigation

  • None filed.

 

State Agency Permitting Timetable for Atlantic Coast Pipeline, Atlantic Coast Pipeline Amendment, Supply Header, and ACP-Piedmont Lease
Responsible State Agency Federal Permit/Review Intermediate Completion Date Final Completion Date Description Field
Virginia Department of Environmental Quality, Coastal Zone Management Program Section 307 CZMA Review N/A TBD The state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016) provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
North Carolina Department of Environment and Natural Resources Section 307 CZMA Review N/A TBD The state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016) provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
West Virginia Department of Environmental Protection, Division of Water and Waste Management Section 401 CWA Review - Water Quality Certification N/A TBD The state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016) provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
Virginia Department of Environmental Quality, Water Division Section 401 CWA Review - Water Quality Certification N/A TBD The state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016) provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
North Carolina Department of Environment and Natural Resources,  Division of Water Resources Section 401 CWA Review - Water Quality Certification N/A TBD The state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016) provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
Pennsylvania Department of Environmental Protection, Bureau of Point and Non-Point Source Management Section 401 CWA Review - Water Quality Certification N/A TBD The state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016) provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
West Virginia Department of Environmental Protection, Division of Water and Waste Management Section 402 CWA Review - National Pollutant Discharge Elimination System, Stormwater General Permit N/A TBD The state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016) provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
Virginia Department of Environmental Quality, Water Division Section 402 CWA Review - National Pollutant Discharge Elimination System, Stormwater General Permit N/A TBD The state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016) provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
North Carolina Department of Environment and Natural Resources - Division of Energy, Mineral, and Land Resources Section 402 CWA Review - National Pollutant Discharge Elimination System, Stormwater General Permit N/A TBD The state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016) provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
West Virginia Department of Environmental Protection, Division of Water and Waste Management Section 402 CWA Review - National Pollutant Discharge Elimination System, Hydrostatic Test Discharge Permit N/A TBD The state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016) provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
Virginia Department of Environmental Quality, Water Division Section 402 CWA Review - National Pollutant Discharge Elimination System, Hydrostatic Test Discharge Permit N/A TBD The state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016) provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
Pennsylvania Department of Environmental Protection, Bureau of Point and Non-Point Source Management Section 402 CWA Review - National Pollutant Discharge Elimination System, Hydrostatic Test Discharge Permit N/A TBD The state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016) provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
West Virginia Department of Environmental Protection, Division of Air Quality Title V CAA Review - Operating Permit for Air Emissions N/A TBD The state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016) provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
Virginia Department of Environmental Quality, Air Division Title V CAA Review - Operating Permit for Air Emissions N/A TBD The state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016) provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
North Carolina Department of Environment and Natural Resources - Division of Air Quality Title V CAA Review - Operating Permit for Air Emissions N/A TBD The state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016) provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
Pennsylvania Department of Environmental Protection, Bureau of Air Quality Title V CAA Review - Operating Permit for Air Emissions N/A TBD The state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016) provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."

 

Last updated February 13, 2018

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete