Project Name:
Responsible Agency:
Fish and Wildlife Service
Agency Status:
Participating
Status:
Complete
Action Outcome:
Biological opinion issued
Description:
The ESA section 7 consultation will evaluate the effects of the proposed projects on Federally listed species and designated Critical Habitat.
Milestones:
ESA Consultation Request Package Submitted (Agency Action)
3811
Completed Date:
FWS determines ESA Consultation Package is Complete - Formal (Agency Action)
3816
Completed Date:
ESA Consultation Concludes (Agency Action)
3821
-
Monthly Status Report for May 2023:BOEM undertook a comprehensive review of the permitting timetable for this project with the cooperating agencies and project sponsor. The review encompassed all NEPA and associated agency actions and milestone dates for the project, including this action. The review culminated in a request from BOEM on May 22, 2023 for an Executive Director Determination to update interim and final completion dates for multiple actions, including this action. On June 6, 2023, the Executive Director made a determination to adjust the permitting timetable as requested, with the exception of this action. Because the Executive Director did not have enough time to make a decision more than 30 days in advance of the completion date of this action, as required under the FAST-Act (42 U.S.C. § 4370m-2(c)(2)(D)(ii)), this action was not modified through the ED Determination and instead followed the non-conformance protocol. The alternative completion date for this action, as set forth in the BOEM request to the Executive Director, was published on the dashboard.
-
Non-conformance Explanation:The USFWS and BOEM agreed to extend the milestone to allow the USFWS sufficient time to incorporate new information that was received into the effects analysis of the Biological Opinion.
Alternative Completion Date: