Project Name:
Responsible Agency:
US Army Corps of Engineers - Regulatory
Status:
Complete
Action Outcome:
Permit issued/verified
Milestones:
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action)
3876
Completed Date:
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action)
3881
Completed Date:
Publication of Public Notice (Agency Action)
3886
Completed Date:
Final Verification/Permit Decision Rendered (Agency Action)
3891
Completed Date: