Project Name:
Responsible Agency:
Bureau of Ocean Energy Management
Status:
Complete
Action Outcome:
Issuance of a joint ROD
Milestones:
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action)
3506
Completed Date:
Scoping (Agency Action)
3511
Completed Date:
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action)
3516
Completed Date:
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
3521
-
Monthly Status Report for December 2024:Joint ROD is on track for execution on Dec 20.
-
Monthly Status Report for November 2024:BOEM published the FEIS on Nov 15 and is on track to meet the Dec 20 ROD milestone.
-
Monthly Status Report for October 2024:BOEM is on track to meet the FEIS milestone next month.
-
Monthly Status Report for September 2024:BOEM is on track to meet the FEIS milestone. BOEM provided cooperators a copy of the redline preliminary FEIS on Sep 16, responsive to agency comment.
-
Monthly Status Report for August 2024:BOEM is on track to meet the milestone FEIS milestone of November 15. BOEM received comment from the cooperators on the preliminary FEIS on Aug 19 and is reviewing their input.
-
Monthly Status Report for July 2024:BOEM is on track to meet the milestone FEIS milestone of November 15. The preliminary FEIS was sent to cooperating agencies in July for their initial round of review and BOEM expects to receive comments by Aug 19.
-
Monthly Status Report for June 2024:BOEM is on track to meet the milestone FEIS milestone of November 15. The preliminary FEIS will be sent out to cooperating agencies in July for their initial round of review.
-
Monthly Status Report for May 2024:BOEM is responding to comments on the DEIS and preparing the preliminary FEIS. BOEM is targeting the end of May to complete internal review. The preliminary FEIS will be sent out to cooperating agencies in July for their initial round of review.
-
Monthly Status Report for April 2024:BOEM is working on responding to comments on the DEIS and preparing the preliminary FEIS. The preliminary FEIS will be sent out to cooperating agencies this July for an initial round of review. BOEM is on track to meet the milestone date.
-
Monthly Status Report for March 2024:BOEM undertook a review of the permitting timetable for this project with the cooperating agencies and in consultation with the Sponsor. The review encompassed all remaining milestone dates for the project, including this one. Based on that review, in December of 2023, BOEM initiated development of a revised permitting timetable. BOEM subsequently participated in 3 convening meetings with the Permitting Council and the Sponsor. BOEM is currently undertaking a final review of the revised permitting timetable to reset the schedule for the remaining milestones.
-
Monthly Status Report for February 2024:BOEM undertook a review of the permitting timetable for this project with the cooperating agencies and in consultation with the Sponsor. The review encompassed all remaining milestone dates for the project, including this one. Based on that review, in December of 2023, BOEM initiated development of a revised permitting timetable. BOEM subsequently participated in 3 convening meetings with the Permitting Council and the Sponsor and currently has a revised permitting timetable before the Permitting Council to reset the schedule for the remaining milestones.
-
Monthly Status Report for January 2024:BOEM undertook a review of the permitting timetable for this project with the cooperating agencies and in consultation with the project sponsor. The review encompassed all agency actions and milestone dates for the project, including this action. Based on that review, in December of 2023, BOEM developed a revised permitting timetable. The Permitting Council has scheduled a convening meeting in February of 2024 to further consult on the proposed timetable.
-
Monthly Status Report for December 2023:BOEM is undertaking a review of the permitting timetable for this project with the cooperating agencies and in consultation with the project sponsor. The review encompasses all agency actions and milestone dates for the project, including this action. The review will result in an updated permitting time table for all actions, including this milestone.
-
Non-conformance Explanation:Pending the Sponsor's submittal to NMFS of supplemental information for their MMPA application, BOEM will undertake a comprehensive review of the permitting timetable for this project with the cooperating agencies and project sponsor. The review will encompass all NEPA and associated agency actions and milestone dates for the project, including this action. Upon completing that review, BOEM will submit to FPISC a request for an Executive Director Determination to update interim and final completion dates for multiple actions, including this action.
Alternative Completion Date:
Issuance of Lead Agency Record of Decision (Agency Action)
3536
Alternative Completion Date: