Environmental Impact Statement (EIS)

Project Name: Responsible Agency:
Bureau of Ocean Energy Management
Status:
Complete
POC Name:
Mary Boatman
POC Title:
Environmental Protection Specialist
Public Participation Website:
Action Outcome:
Issuance of a joint ROD

Milestones:

Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action)
Completed Date:
Scoping (Agency Action)
Completed Date:
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action)
Completed Date:
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
Completed Date:
Issuance of Lead Agency Record of Decision (Agency Action)
  • Non-conformance Explanation:
    Missed Date Explanation (Published 10/21/2021): The 10/20/2021 completion date for "Issuance of Lead Agency Record of Decision" was missed because the Executive Director did not timely receive a  request to modify the completion date. 42 U.S.C. 4370m-2(c)(2)(D)(i)(III) & (ii). Consultations under Section 106 of the National Historic Preservation Act are ongoing. Consulting parties requested additional time to review the Section 106 Memorandum of Agreement (MOA). The Record of Decision cannot be issued until the completion of the Section 106 process (i.e., execution of the MOA). In accordance with 42 U.S.C. 4370m-2(c)(2)(F)(ii), BOEM has established an alternative completion date of 11/23/2021.
Alternative Completion Date:
11/23/2021