Description:
On 11/06/2013, the project sponsor requested that FERC put a hold on the licensing process, pending the resolution of issues pertaining to interconnection of the project to the transmission grid. The project sponsor filed a supplemental license application on 11/24/2015 to extend the proposed project transmission line by 11 miles. FERC staff issued an Additional Information Request on 04/06/2016, to obtain additional information from the project sponsor. Licensing was completed on 02/17/2017.