Cooperating under NEPA
Description:
The proposed project may affect pallid sturgeion, however, it cannot be determined at this time whether those impacts would result in a "likely" or "not likely to adversely affect" situtation. Further consultation with the Louisiana Ecological Services Office is therefore necessary. The target date for final completion is 135 days after all information (a complete consultation package) is received. Conclusion of ESA consultation is dependent on FWS receiving a complete BA.
Milestones:
-
Environmental Impact Statement (EIS)
:
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action)
- Completed Date: 03/05/2021
Target Completion is 135 days after all information is received. The Service revised the schedule to reflect our agreement with the Corps for a 30-day extension to allow adequate time for their review and comment on the draft biological opinion.