Project Name:
Responsible Agency:
Utah
Status:
Public Participation Website:
Complete
Public Participation Website
Action Outcome:
Issuance of a single combined FEIS-ROD
Description:
The Utah Department of Transportation (UDOT) is preparing the Parley’s Interchange Environmental Impact Statement (EIS) to evaluate the short- and long-term needs of the I-80/I-215 eastside interchange. The purpose of the study is to improve safety, reduce congestion, increase regional mobility and update the current design of the interchange.
Milestones:
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action)
3506
Completed Date:
Scoping (Agency Action)
3511
Completed Date:
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action)
3516
Completed Date:
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
3521
Completed Date:
Issuance of Lead Agency Record of Decision (Agency Action)
3536
-
Section 106 Review
:
Section 106 consultation concluded (Agency Action)
- Completed Date: 05/20/2019 -
Endangered Species Act Consultation (DOI-FWS)
:
ESA Consultation Concludes (Agency Action)
- Completed Date: 06/06/2019
Completed Date: