Description:
DOE has jurisdiction under the Natural Gas Act, Sections 3(a) and 3(c), for the permitting of natural gas exports from the United States. The application under Section 3(a) was subject to NEPA review.
Milestones:
-
Authorization for Liquefied Natural Gas Terminal Facilities, Onshore or in State Waters
:
Final decision/agency action (Agency Action)
- Completed Date: 11/17/2022
DOE issued a conditional authorization to Commonwealth LNG for export of LNG to non-Free Trade Agreement nations under section 3(a) of the Natural Gas Act (15 U.S.C. § 717b) on February 14, 2025. On August 29, 2025, DOE issued the final authorization.