Description:
ESA-listed species exist in the area affected by the proposed project and the proposed action has the potential to affect these resources. Therefore, ESA Section 7 consultation is required. The final completion date is contingent upon NMFS receiving sufficient information to initiate consultation. Formal consultation requires at least 135 days following the consultation initiation date.
Milestones:
-
Environmental Impact Statement (EIS)
:
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action)
- Completed Date: 03/31/2022
This target timeline is dependent on receipt of a consultation request from FERC, consisting of a Biological Assessment.
The final completion date is contingent upon NMFS receiving sufficient information that NMFS deems adequate to initiate the ESA consultation.