Project Name:
Responsible Agency:
Cooperating under NEPA
Fish and Wildlife Service
Agency Status:
Cooperating under FAST-41Cooperating under NEPA
Status:
Complete
Action Outcome:
Biological opinion issued
Description:
FWS received a complete and sufficient Biological Assessment on November 3, 2018 and anticipated concluding consultation within the 135 days provided by statute; however, due to a lapse in appropriations the governement was shut down for 35 days. FWS concluded consultation with the issuance of a Biological Opinion on April 22, 2019.
Milestones:
ESA Consultation Request Package Submitted (Agency Action)
3811
Completed Date:
FWS determines ESA Consultation Package is Complete - Formal (Agency Action)
3816
Completed Date:
ESA Consultation Concludes (Agency Action)
3821
Completed Date: